6518 N WHITMAN AVE 91406
Certificate Information: 6518 N WHITMAN AVE 91406
- Application / Permit
- 21016-30000-32362
- Plan Check / Job No.
- B21WL04313
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Enclose (e) proch to (e) 1-story SFD.
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/28/2021
Permit Application Status History
| Submitted | 9/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | MANUEL GARCIA |
| Corrections Issued | 9/30/2021 | MANUEL GARCIA |
| Plan Check Approved | 10/28/2021 | MANUEL GARCIA |
| Issued | 11/2/2021 | APPLICANT |
| Building Plans Picked Up | 11/3/2021 | APPLICANT |
| Permit Finaled | 12/27/2021 | RAUL OLAGI |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 10/20/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/5/2021 | Partial Approval | RAUL OLAGI |
| Deputy Drilled-In Anchors | 11/5/2021 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 11/5/2021 | Approved | RAUL OLAGI |
| MERV13>=Rough | 11/5/2021 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 11/5/2021 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 11/17/2021 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2021 | Approved | RAUL OLAGI |
| HVAC-Rough | 11/17/2021 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 11/17/2021 | Corrections Issued | RAUL OLAGI |
| Shower Pan | 11/19/2021 | No Access for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 11/22/2021 | Approved | RAUL OLAGI |
| HVAC-Rough | 11/22/2021 | Partial Approval | RAUL OLAGI |
| Interior/Exterior Lathing | 11/22/2021 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 11/22/2021 | Approved | RAUL OLAGI |
| Shower Pan | 11/22/2021 | Approved | RAUL OLAGI |
| Drywall Nailing | 11/23/2021 | Approved | RAUL OLAGI |
| Insulation | 11/23/2021 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/23/2021 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/16/2021 | Corrections Issued | RAUL OLAGI |
| Final | 12/16/2021 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 12/16/2021 | Approved | RAUL OLAGI |
| MERV13>=Final | 12/16/2021 | Approved | RAUL OLAGI |
| PLUMBING-Final | 12/16/2021 | Approved | RAUL OLAGI |
| Smoke Detectors | 12/16/2021 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/27/2021 | Approved | RAUL OLAGI |
| Final | 12/27/2021 | Permit Finaled | RAUL OLAGI |