12130 W GREENE AVE 90066
Certificate Information: 12130 W GREENE AVE 90066
- Application / Permit
- 21016-30000-32036
- Plan Check / Job No.
- B21WL04294
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage to ADU per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/27/2022
- Issuing Office
- Current Status
- CofO Issued on 7/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2021 | JASON JANGADA |
| Corrections Issued | 9/30/2021 | JASON JANGADA |
| Applicant returned to address corrections | 12/23/2021 | JASON JANGADA |
| Applicant returned to address corrections | 1/10/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 1/11/2022 | EDWIN ESPIN |
| Plan Check Approved | 1/25/2022 | SAMUEL GONZALEZ |
| Issued | 1/27/2022 | APPLICANT |
| Building Plans Picked Up | 2/1/2022 | APPLICANT |
| CofO in Progress | 7/6/2022 | PATRICK QUALEY |
| Permit Finaled | 7/18/2022 | DANIEL ORRANTE |
| CofO Issued | 7/18/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/18/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 10/12/2021 | SAUL GARCIA |
| Specific Plan | Cleared | 11/16/2021 | VALERIA CEJA |
| Construction near power lines | Cleared | 12/15/2021 | RIDWAN HARDY |
| Address approval | Cleared | 12/29/2021 | SAUL GARCIA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/8/2022 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 2/8/2022 | Partial Approval | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 2/25/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/25/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/30/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 3/30/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/30/2022 | Corrections Issued | STEPHANIE SWANSON |
| Wood Frame | 3/30/2022 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/7/2022 | Conditional Approval | PATRICK QUALEY |
| ELECTRICAL-Rough | 4/7/2022 | Approved | PATRICK QUALEY |
| Green Building Rough | 4/7/2022 | Conditional Approval | PATRICK QUALEY |
| Interior/Exterior Lathing | 4/7/2022 | Approved | PATRICK QUALEY |
| PLUMBING-Rough | 4/7/2022 | Corrections Issued | PATRICK QUALEY |
| HVAC-Rough | 4/12/2022 | Approved | RYAN SALAZAR |
| Insulation | 4/12/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 4/12/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 4/18/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/24/2022 | Approved | PATRICK QUALEY |
| Final | 5/24/2022 | Corrections Issued | PATRICK QUALEY |
| Green Building Final | 5/24/2022 | Corrections Issued | PATRICK QUALEY |
| Green Building Rough | 5/24/2022 | Approved | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Not Ready | PATRICK QUALEY |
| Smoke Detectors | 5/24/2022 | Approved | PATRICK QUALEY |
| Final | 5/31/2022 | Corrections Issued | PATRICK QUALEY |
| Green Building Final | 5/31/2022 | Approved | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 5/31/2022 | SGSOV Not Ready | PATRICK QUALEY |
| Final | 6/24/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 6/24/2022 | SGSOV Not Ready | STEPHANIE SWANSON |
| Final | 7/1/2022 | Conditional Approval | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Approved | PATRICK QUALEY |
| ELECTRICAL-Final | 7/6/2022 | Approved | PATRICK QUALEY |
| Final | 7/6/2022 | OK to Issue CofO | PATRICK QUALEY |
| HVAC-Final | 7/6/2022 | Approved | PATRICK QUALEY |
| PLUMBING-Final | 7/6/2022 | Approved | PATRICK QUALEY |