1018 S HILGARD AVE 90024

Certificate Information: 1018 S HILGARD AVE 90024

Application / Permit
21016-30000-30465
Plan Check / Job No.
B21WL04172
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(6) Church
Work Description
Interior / extrerior remodel to (e) church including change of interior layout, changeout doors & windows, restrooms accessibility upgrade
Permit Issued
Issued on 9/13/2022
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 8/28/2025

Permit Application Status History

Submitted 9/19/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 REZA HAGHIGHAT
Corrections Issued 10/16/2021 REZA HAGHIGHAT
Quality Review Completed 10/27/2021 TARIK SAOUD
Disabled Access Plans Picked Up 12/9/2021 APPLICANT
Plan Check Approved 8/16/2022 REZA HAGHIGHAT
Building Plans Picked Up 8/24/2022 APPLICANT
Issued 9/13/2022 APPLICANT
Permit Finaled 8/28/2025 RICARDO ROBLES

Permit Application Clearance Information

"Q" conditions Cleared 11/5/2021 ANACANY HURTADO
ZA Case Cleared 11/5/2021 ANACANY HURTADO
ZA Case Cleared 11/5/2021 ANACANY HURTADO
Specific Plan Cleared 11/9/2021 KEVIN FULTON
Fire Marshal Fire Life Safety Cleared 6/22/2022 ANDREW KO
Green Code Cleared 7/12/2022 RICHARD GARCIA
DAS Clearance Cleared 7/22/2022 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 8/16/2022 REZA HAGHIGHAT

Contact Information

Architect Bonneau,, Kirstyn I; Lic. No.: C36535 234 E. COLORADO BLVD STE. 700      PASADENA, CA 91101
Contractor Del Amo Construction Inc; Lic. No.: 744458-B 23840 MADISON STREET      TORRANCE, CA 90505
Engineer Kelly,, John Roland; Lic. No.: C36693 865 RIDGESIDE DR      MONROVIA, CA 91016
Engineer Schulz,, Les Eric; Lic. No.: S2570 346 N LIMA      SIERRA MADRE, CA 91024
Geologist , ; Lic. No.: GEO3092 26632 EL TOBOSO      MISSION VIEJO, C 92691

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/18/2023 Approved PAUL DAVIDSON
Wood Frame 6/12/2023 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 6/14/2023 Partial Approval PAUL DAVIDSON
Pre-Inspection 6/21/2023 Approved PAUL DAVIDSON
Masonry Wall/Backfill 6/27/2023 Partial Approval PAUL DAVIDSON
Footing/Foundation/Slab 7/5/2023 Partial Approval PAUL DAVIDSON
Footing/Foundation/Slab 7/27/2023 Partial Approval PAUL DAVIDSON
Deputy Reinf. Concrete 7/31/2023 Conditional Approval PAUL DAVIDSON
Footing/Foundation/Slab 8/9/2023 Partial Approval PAUL DAVIDSON
Footing/Foundation/Slab 8/15/2023 Approved PAUL DAVIDSON
Drywall Nailing 12/12/2023 Not Ready for Inspection PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Partial Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 1/11/2024 Conditional Approval PAUL DAVIDSON
Footing/Foundation/Slab 1/12/2024 Approved PAUL DAVIDSON
Insulation 2/15/2024 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 2/15/2024 Corrections Issued PAUL DAVIDSON
Wood Frame 2/20/2024 Partial Approval PAUL DAVIDSON
Drywall Nailing 2/26/2024 Not Ready for Inspection CASIMIR BRITTON
Insulation 2/26/2024 Approved CASIMIR BRITTON
Drywall Nailing 3/1/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 3/13/2024 Not Ready for Inspection PAUL DAVIDSON
Interior/Exterior Lathing 3/22/2024 Approved RICARDO ROBLES
Drywall Nailing 3/26/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 4/8/2024 No Access for Inspection PAUL DAVIDSON
Drywall Nailing 4/10/2024 Partial Approval PAUL DAVIDSON
Insulation 4/18/2024 Partial Approval RICARDO ROBLES
T-Bar Ceiling 4/18/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 4/22/2024 Partial Approval PAUL DAVIDSON
Drywall Nailing 4/26/2024 Partial Approval GRANT WOODS
Drywall Nailing 5/6/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 5/6/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 5/9/2024 Approved PAUL DAVIDSON
T-Bar Ceiling 8/6/2024 Not Ready for Inspection PAUL DAVIDSON
Special/Order Compliance 8/9/2024 Partial Inspection PAUL DAVIDSON
T-Bar Ceiling 8/16/2024 Not Ready for Inspection GRANT WOODS
T-Bar Ceiling 11/13/2024 Approved DANIEL VARNUM
Final 7/30/2025 Not Ready for Inspection RICARDO ROBLES
Green Building Final 7/30/2025 Approved RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 7/30/2025 SGSOV Approved RICARDO ROBLES
Smoke Detectors 7/30/2025 Approved RICARDO ROBLES
Final 8/28/2025 Permit Finaled RICARDO ROBLES