21035-21037 W INGOMAR ST 91304

Certificate Information: 21035-21037 W INGOMAR ST 91304

Application / Permit
21016-30000-29803
Plan Check / Job No.
B21WL04071
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert attahced garage in the front of (E) SFD to ADU per CA G.C.S. 65852.2 (e)(1)(A).
Permit Issued
Issued on 1/19/2022
Issuing Office
Current Status
CofO Issued on 5/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 KHUONG TRUONG
Corrections Issued 9/18/2021 KHUONG TRUONG
Applicant returned to address corrections 1/4/2022 JAHANSHAH POURHASSAN
Plan Check Approved 1/5/2022 JAHANSHAH POURHASSAN
Issued 1/19/2022 APPLICANT
Building Plans Picked Up 1/24/2022 APPLICANT
CofO in Progress 5/11/2022 STEVEN BACK
Permit Finaled 5/12/2022 MICHAEL SMITH
CofO Issued 5/12/2022 MICHAEL SMITH
Permit Finaled 5/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/28/2021 CARLOS AGUILERA
Sewer availability Cleared 9/28/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/29/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 12/16/2021 GREGORY HOERNER

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/2/2022 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 2/3/2022 Approved STEVEN BACK
PLUMBING-Rough 2/3/2022 Partial Approval STEVEN BACK
ELECTRICAL-Rough 3/3/2022 Not Ready for Inspection STEVEN BACK
HVAC-Rough 3/3/2022 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 3/3/2022 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 3/8/2022 Approved STEVEN BACK
HVAC-Rough 3/8/2022 Approved STEVEN BACK
Interior/Exterior Lathing 3/8/2022 Partial Approval STEVEN BACK
PLUMBING-Rough 3/8/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 3/11/2022 Approved STEVEN BACK
Green Building Rough 3/11/2022 Approved STEVEN BACK
Insulation 3/14/2022 Approved JESUS PINEDA
Drywall Nailing 3/16/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 3/16/2022 Approved JESUS PINEDA
Final 4/26/2022 Corrections Issued STEVEN BACK
Green Building Final 4/26/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 4/26/2022 SGSOV Not Ready STEVEN BACK
Smoke Detectors 4/26/2022 Approved STEVEN BACK
Final 5/5/2022 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/5/2022 SGSOV Approved STEVEN BACK
Final 5/11/2022 OK to Issue CofO STEVEN BACK