8875 1/2 W CATTARAUGUS AVE 90034
Certificate Information: 8875 1/2 W CATTARAUGUS AVE 90034
- Application / Permit
- 21016-30000-29711
- Plan Check / Job No.
- B21WL04060
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Converting (E) 1-Car Garage to an ADU per CA G.C.S. 65852.2(e)(1)(A) at Rear of Lot.
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Current Status
- Issued on 8/29/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 9/16/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 7/14/2022 | DAVID CASTILLO |
| Issued | 8/29/2022 | APPLICANT |
| Building Plans Picked Up | 8/31/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2021 | WALLIE JONG |
| Specific Plan | Cleared | 9/27/2021 | DYLAN SITTIG |
| Hydrant and Access approval | Cleared | 11/10/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lobnan,, Essam; Lic. No.: C78053 | PO BOX 64373 LOS ANGELES, CA 90064 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/24/2023 | Corrections Issued | JEREMY TODD |
| Grading Pre-Inspection | 10/2/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Pre-Inspection | 10/2/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Underground Mechanical | 10/2/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Pre-Inspection | 10/7/2024 | Approved | MEL KHACHATOURIAN |
| Special/Order Compliance | 10/7/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Underground Mechanical | 10/7/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Underground Mechanical | 10/17/2024 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 10/28/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Underground Mechanical | 10/28/2024 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 10/31/2024 | Partial Approval | MEL KHACHATOURIAN |
| Underground Mechanical | 10/31/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Sewer | 11/1/2024 | Approved | BOBBY KEY |
| Underground Mechanical | 11/1/2024 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 11/5/2024 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 12/11/2024 | Partial Inspection | ARAM AVEDISIAN |
| Special/Order Compliance | 12/16/2024 | Partial Approval | SEAN HAUPT |
| Wood Frame | 12/16/2024 | Not Ready for Inspection | SEAN HAUPT |
| Wood Frame | 12/19/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 2/18/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 2/18/2025 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/20/2025 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 5/20/2025 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 5/20/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 5/20/2025 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 5/30/2025 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 5/30/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 6/12/2025 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 6/24/2025 | Approved | EVAN COOPER |
| Insulation | 6/24/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 1/5/2026 | Approved | EVAN COOPER |
| Final | 6/1/2026 | Partial Inspection | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 6/1/2026 | SGSOV Not Ready | WILBER ROSALES |
| Interior/Exterior Lathing | 6/11/2026 | Approved | WILBER ROSALES |