4220 S MICHAEL AVE 90066
Certificate Information: 4220 S MICHAEL AVE 90066
- Application / Permit
- 21016-30000-27403
- Plan Check / Job No.
- B21WL04023
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- interior remodel: kitchen remodel & remove interior bearing wall and exterior alterations, interior remodel of bathroom
- Permit Issued
- Issued on 7/13/2022
- Issuing Office
- Current Status
- Permit Finaled on 3/29/2023
Permit Application Status History
| Submitted | 9/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2021 | MANUEL GARCIA |
| Corrections Issued | 9/13/2021 | MANUEL GARCIA |
| Plan Check Approved | 6/14/2022 | CHIHARU SUZUKI |
| Issued | 7/13/2022 | APPLICANT |
| Building Plans Picked Up | 7/27/2022 | APPLICANT |
| Permit Finaled | 3/28/2023 | EVAN COOPER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | T J D Construction Inc; Lic. No.: 594756-B | 27929 FEATHERSTAR AVENUE SANTA CLARA, CA 91350 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/3/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/3/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/30/2022 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/30/2022 | Partial Approval | JESUS RODRIGUEZ |
| Structural Steel Frame | 8/30/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/13/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/13/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 9/13/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/13/2022 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/14/2022 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/14/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 9/14/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 9/14/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/14/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/14/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 9/14/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/15/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 9/19/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 9/27/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 10/5/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 1/26/2023 | Corrections Issued | HERBERT GIRON |
| Final | 1/26/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 1/26/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 1/26/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 1/26/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 3/28/2023 | Approved | EVAN COOPER |
| Final | 3/28/2023 | Permit Finaled | EVAN COOPER |