4220 S MICHAEL AVE 90066

Certificate Information: 4220 S MICHAEL AVE 90066

Application / Permit
21016-30000-27403
Plan Check / Job No.
B21WL04023
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
interior remodel: kitchen remodel & remove interior bearing wall and exterior alterations, interior remodel of bathroom
Permit Issued
Issued on 7/13/2022
Issuing Office
Current Status
Permit Finaled on 3/29/2023

Permit Application Status History

Submitted 9/10/2021 APPLICANT
Assigned to Plan Check Engineer 9/13/2021 MANUEL GARCIA
Corrections Issued 9/13/2021 MANUEL GARCIA
Plan Check Approved 6/14/2022 CHIHARU SUZUKI
Issued 7/13/2022 APPLICANT
Building Plans Picked Up 7/27/2022 APPLICANT
Permit Finaled 3/28/2023 EVAN COOPER

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor T J D Construction Inc; Lic. No.: 594756-B 27929 FEATHERSTAR AVENUE      SANTA CLARA, CA 91350

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/3/2022 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 8/3/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 8/30/2022 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 8/30/2022 Partial Approval JESUS RODRIGUEZ
Structural Steel Frame 8/30/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/13/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 9/13/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 9/13/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 9/13/2022 Conditional Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/14/2022 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 9/14/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 9/14/2022 Approved JESUS RODRIGUEZ
Insulation 9/14/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 9/14/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 9/14/2022 Approved JESUS RODRIGUEZ
Shower Pan 9/14/2022 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 9/15/2022 Approved JESUS RODRIGUEZ
Shower Pan 9/19/2022 Approved DAVID FEILER
Drywall Nailing 9/27/2022 Approved DAVID FEILER
Interior/Exterior Lathing 10/5/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 1/26/2023 Corrections Issued HERBERT GIRON
Final 1/26/2023 Corrections Issued HERBERT GIRON
HVAC-Final 1/26/2023 Approved HERBERT GIRON
PLUMBING-Final 1/26/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/26/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 1/26/2023 Approved HERBERT GIRON
ELECTRICAL-Final 3/28/2023 Approved EVAN COOPER
Final 3/28/2023 Permit Finaled EVAN COOPER