1200 N GETTY CENTER DR 90049

Certificate Information: 1200 N GETTY CENTER DR 90049

Application / Permit
21016-30000-25884
Plan Check / Job No.
B21WL03994
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Tenant improvment (interior remodel 16,050 sf) to existing research lab (within existing Getty Center) to modernize existing lab and office spaces. no change of use, occupancy, floor area, and no exterior work.
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
Permit Finaled on 5/19/2025

Permit Application Status History

Submitted 9/10/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 ALFREDO JARA
Corrections Issued 10/5/2021 ALFREDO JARA
Quality Review Completed 10/15/2021 TARIK SAOUD
Disabled Access Plans Picked Up 10/29/2021 APPLICANT
Applicant returned to address corrections 12/14/2021 ALFREDO JARA
Applicant returned to address corrections 12/15/2021 ALFREDO JARA
Applicant returned to address corrections 12/16/2021 ALFREDO JARA
Building Plans Picked Up 1/7/2022 APPLICANT
Green Plans Picked Up 4/15/2022 APPLICANT
Plan Check Approved 4/28/2022 ALFREDO JARA
Issued 5/17/2022 APPLICANT
Permit Finaled 5/20/2025 CASIMIR BRITTON

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 1/3/2022 RONILO MULAWIN
DAS Clearance Cleared 3/31/2022 ALFREDO JARA
Green Code Cleared 4/14/2022 RICHARD GARCIA

Contact Information

Contractor Rudolph & Sletten Inc; Lic. No.: 198069-B 2 CIRCLE STAR WAY 4TH FLOOR      SAN CARLOS, CA 94070
Engineer Sabol,, Thomas Andrew; Lic. No.: S3175 888 S FIGUEROA ST 18TH FL      LOS ANGELES, CA 90017

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/8/2022 Approved SORIN CIRSTOIU
Pre-Inspection 8/8/2022 Partial Inspection SORIN CIRSTOIU
Deputy Drilled-In Anchors 8/18/2022 Conditional Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 8/19/2022 Conditional Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 8/24/2022 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 8/24/2022 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 8/29/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 8/30/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 9/1/2022 Approved SORIN CIRSTOIU
Footing/Foundation/Slab 9/1/2022 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 10/5/2022 Partial Approval GRANT WOODS
Drywall Nailing 11/7/2022 Partial Approval SORIN CIRSTOIU
Wood Frame 11/9/2022 Partial Approval SORIN CIRSTOIU
Drywall Nailing 11/30/2022 Partial Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 12/1/2022 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 12/14/2022 Partial Approval FARHAD DADBIN
Deputy Drilled-In Anchors 12/28/2022 Conditional Approval SORIN CIRSTOIU
Wood Frame 12/30/2022 Partial Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 1/19/2023 Partial Approval MICHAEL PETRUSKO
Deputy Steel/Welding 1/25/2023 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 1/26/2023 Approved SORIN CIRSTOIU
Deputy Steel/Welding 1/27/2023 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 1/30/2023 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 2/7/2023 Partial Approval SORIN CIRSTOIU
Deputy Steel/Welding 2/8/2023 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 2/9/2023 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 2/17/2023 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 3/3/2023 Conditional Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 3/9/2023 Conditional Approval SORIN CIRSTOIU
T-Bar Ceiling 3/13/2023 Partial Inspection SORIN CIRSTOIU
Deputy Drilled-In Anchors 3/16/2023 Conditional Approval SORIN CIRSTOIU
Deputy Fireproofing 4/6/2023 Conditional Approval SORIN CIRSTOIU
Deputy Fireproofing 4/12/2023 Conditional Approval MICHAEL PETRUSKO
T-Bar Ceiling 5/4/2023 Partial Approval SORIN CIRSTOIU
Deputy Steel/Welding 5/10/2023 Conditional Approval SORIN CIRSTOIU
T-Bar Ceiling 6/8/2023 Conditional Approval GRANT WOODS
T-Bar Ceiling 6/29/2023 Conditional Approval FARHAD DADBIN
Deputy Drilled-In Anchors 7/13/2023 Conditional Approval ALAN NOVAK
Deputy Other (see comments) 7/24/2023 Conditional Approval SORIN CIRSTOIU
T-Bar Ceiling 7/27/2023 Partial Approval SORIN CIRSTOIU
Special/Order Compliance 11/15/2024 Partial Approval CASIMIR BRITTON
Final 4/29/2025 Not Ready for Inspection CASIMIR BRITTON
Green Building Final 4/29/2025 Approved CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 4/29/2025 SGSOV Not Ready CASIMIR BRITTON
Smoke Detectors 4/29/2025 Not Ready for Inspection CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 5/16/2025 SGSOV Not Ready CASIMIR BRITTON
Final 5/20/2025 Permit Finaled CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Approved CASIMIR BRITTON
Smoke Detectors 5/20/2025 Approved CASIMIR BRITTON