12128 W GREENE AVE 90066
Certificate Information: 12128 W GREENE AVE 90066
- Application / Permit
- 21016-30000-23763
- Plan Check / Job No.
- B21WL03882
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel of (E) SFD to relocate bedroom, add master bathroom and closet, and laundry closet, (N) bathroom and kichen remodel.
- Permit Issued
- Issued on 9/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 7/5/2022
Permit Application Status History
| Submitted | 9/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 9/3/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 9/14/2021 | RICHARD GARCIA |
| Issued | 9/20/2021 | APPLICANT |
| Permit Finaled | 7/5/2022 | PATRICK QUALEY |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 11/16/2021 | Corrections Issued | DEANDRE HOFFMAN |
| Wood Frame | 11/18/2021 | Corrections Issued | ENRIQUE MIRELES |
| Drywall Nailing | 11/23/2021 | Partial Approval | DAVID FEILER |
| Wood Frame | 11/23/2021 | Corrections Issued | DAVID FEILER |
| Deputy Wood Construction | 12/6/2021 | Partial Approval | JOHN KAYON |
| Wood Frame | 12/17/2021 | Approved | ENRIQUE MIRELES |
| Final | 5/13/2022 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 5/13/2022 | SGSOV Not Ready | STEPHANIE SWANSON |
| Smoke Detectors | 5/13/2022 | Approved | STEPHANIE SWANSON |
| Final | 5/24/2022 | Corrections Issued | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Not Ready | PATRICK QUALEY |
| Final | 5/31/2022 | Corrections Issued | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 5/31/2022 | SGSOV Approved | PATRICK QUALEY |
| Final | 6/24/2022 | Partial Approval | STEPHANIE SWANSON |
| Final | 7/5/2022 | Permit Finaled | PATRICK QUALEY |