364 N ORLANDO AVE 90048
Certificate Information: 364 N ORLANDO AVE 90048
- Application / Permit
- 21016-30000-22961
- Plan Check / Job No.
- B21WL03832
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage to accessory dwelling unit per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/2/2022
- Issuing Office
- Current Status
- CofO Issued on 7/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2021 | JASON JANGADA |
| Corrections Issued | 9/3/2021 | JASON JANGADA |
| Applicant returned to address corrections | 2/26/2022 | JASON JANGADA |
| Applicant returned to address corrections | 3/17/2022 | JASON JANGADA |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Applicant returned to address corrections | 4/4/2022 | JASON JANGADA |
| Applicant returned to address corrections | 4/30/2022 | JASON JANGADA |
| Plan Check Approved | 5/25/2022 | JASON JANGADA |
| Issued | 6/2/2022 | APPLICANT |
| CofO in Progress | 7/1/2022 | ADAM ESCOTO |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
| CofO Issued | 7/9/2022 | DEROLD HAUFF |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/14/2021 | JEANIE LAM |
| Sewer availability | Cleared | 12/14/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2021 | JEANIE LAM |
| Construction near power lines | Cleared | 1/7/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 2/17/2022 | JOHN CONNEALLY |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Namdar,, Mansour Tom; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/6/2022 | Approved | JOSEPH MCGARRY |
| Final | 6/6/2022 | Corrections Issued | JOSEPH MCGARRY |
| METHANE-Final | 6/6/2022 | Approved | JOSEPH MCGARRY |
| METHANE-Rough | 6/6/2022 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 6/6/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 6/6/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 7/1/2022 | Approved | ADAM ESCOTO |
| Final | 7/1/2022 | OK to Issue CofO | ADAM ESCOTO |
| HVAC-Final | 7/1/2022 | Approved | ADAM ESCOTO |
| PLUMBING-Final | 7/1/2022 | Approved | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Approved | ADAM ESCOTO |