2005 W 96TH ST 90047
Certificate Information: 2005 W 96TH ST 90047
- Application / Permit
- 21016-30000-22719
- Plan Check / Job No.
- B21WL03805
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-2" X 20'-2" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ADD 3' X 6'-4" FOR EXTERIOR LAUNDRY ROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/5/2022
- Issuing Office
- Current Status
- CofO Issued on 10/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2021 | RAPHAEL ROSAS |
| Corrections Issued | 9/7/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/26/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/27/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 3/28/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Issued | 7/5/2022 | APPLICANT |
| CofO in Progress | 9/25/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 10/2/2025 | DEROLD HAUFF |
| CofO Issued | 10/2/2025 | DEROLD HAUFF |
| Permit Finaled | 10/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2021 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 12/10/2021 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 12/10/2021 | CHRISTOPHER ROCHA |
| Construction near power lines | Cleared | 3/15/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/20/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 2/10/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/18/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/18/2024 | Approved | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 4/18/2024 | Corrections Issued | JOSE MACIAS |
| Wood Frame | 4/18/2024 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 3/20/2025 | Corrections Issued | JOSE MACIAS |
| Underground Mechanical | 3/20/2025 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 4/9/2025 | Conditional Approval | WAYNE REGESTER |
| Insulation | 4/16/2025 | Approved | WAYNE REGESTER |
| Shower Pan | 4/16/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 5/2/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 5/2/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 7/24/2025 | Approved | WAYNE REGESTER |
| Final | 7/24/2025 | Corrections Issued | WAYNE REGESTER |
| Footing/Foundation/Slab | 7/24/2025 | Approved | WAYNE REGESTER |
| Green Building Final | 7/24/2025 | Corrections Issued | WAYNE REGESTER |
| Green Building Rough | 7/24/2025 | Approved | WAYNE REGESTER |
| METHANE-Barrier | 7/24/2025 | Approved | WAYNE REGESTER |
| METHANE-Final | 7/24/2025 | Approved | WAYNE REGESTER |
| METHANE-Rough | 7/24/2025 | Approved | WAYNE REGESTER |
| METHANE-Subgrade | 7/24/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 7/24/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Smoke Detectors | 7/24/2025 | Approved | WAYNE REGESTER |
| Final | 8/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 8/29/2025 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Final | 9/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 9/5/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Final | 9/15/2025 | Corrections Issued | BARRY HACHE |
| Service/Power Release | 9/15/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 9/24/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| Service/Power Release | 9/24/2025 | Approved | SALVADOR MARTINEZ |