2236 W 28TH ST 90018
Certificate Information: 2236 W 28TH ST 90018
- Application / Permit
- 21016-30000-21107
- Plan Check / Job No.
- B21WL03638
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) garage to ADU per GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 7/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2021 | MANUEL GARCIA |
| Corrections Issued | 8/17/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/16/2021 | JASON JANGADA |
| Applicant returned to address corrections | 1/7/2022 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 1/24/2022 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 2/10/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 2/19/2022 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 2/23/2022 | JAHANSHAH POURHASSAN |
| Issued | 3/17/2022 | APPLICANT |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| CofO in Progress | 6/20/2023 | SABAS ALONSO |
| Permit Finaled | 7/1/2023 | DEROLD HAUFF |
| CofO Issued | 7/1/2023 | DEROLD HAUFF |
| Permit Finaled | 7/1/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 8/27/2021 | MAX LODER |
| Address approval | Cleared | 9/3/2021 | THOMAS LANG |
| Sewer availability | Cleared | 9/3/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | THOMAS LANG |
| Construction near power lines | Cleared | 11/8/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 12/6/2021 | ROBERT DUFF |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/23/2022 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 6/23/2022 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 7/26/2022 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 7/29/2022 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/1/2022 | Partial Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/1/2022 | Approved | MICHAEL LEWIS |
| Green Building Rough | 9/1/2022 | Partial Inspection | MICHAEL LEWIS |
| HVAC-Rough | 9/1/2022 | Partial Approval | MICHAEL LEWIS |
| METHANE-Rough | 9/1/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 9/1/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/12/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 9/12/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 9/12/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 9/19/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/19/2022 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 9/20/2022 | Approved | SABAS ALONSO |
| Shower Pan | 9/20/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 3/29/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/29/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/29/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 3/31/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 3/31/2023 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 3/31/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 4/12/2023 | Not Ready for Inspection | SABAS ALONSO |
| Final | 4/12/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 4/12/2023 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 4/12/2023 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 4/12/2023 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 4/12/2023 | SGSOV Approved | SABAS ALONSO |
| ELECTRICAL-Final | 4/17/2023 | Approved | SABAS ALONSO |
| Final | 4/17/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 4/17/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 4/17/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 4/17/2023 | Approved | SABAS ALONSO |
| Final | 4/24/2023 | Conditional Approval | SABAS ALONSO |
| Final | 6/20/2023 | OK to Issue CofO | SABAS ALONSO |