2236 W 28TH ST 90018

Certificate Information: 2236 W 28TH ST 90018

Application / Permit
21016-30000-21107
Plan Check / Job No.
B21WL03638
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) garage to ADU per GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 3/17/2022
Issuing Office
Current Status
CofO Issued on 7/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2021 APPLICANT
Assigned to Plan Check Engineer 8/13/2021 MANUEL GARCIA
Corrections Issued 8/17/2021 MANUEL GARCIA
Applicant returned to address corrections 9/16/2021 JASON JANGADA
Applicant returned to address corrections 1/7/2022 JAHANSHAH POURHASSAN
Applicant returned to address corrections 1/24/2022 JAHANSHAH POURHASSAN
Applicant returned to address corrections 2/10/2022 RICHARD GARCIA
Applicant returned to address corrections 2/19/2022 JAHANSHAH POURHASSAN
Plan Check Approved 2/23/2022 JAHANSHAH POURHASSAN
Issued 3/17/2022 APPLICANT
Building Plans Picked Up 3/18/2022 APPLICANT
CofO in Progress 6/20/2023 SABAS ALONSO
Permit Finaled 7/1/2023 DEROLD HAUFF
CofO Issued 7/1/2023 DEROLD HAUFF
Permit Finaled 7/1/2023 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 8/27/2021 MAX LODER
Address approval Cleared 9/3/2021 THOMAS LANG
Sewer availability Cleared 9/3/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 9/8/2021 THOMAS LANG
Construction near power lines Cleared 11/8/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 12/6/2021 ROBERT DUFF

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/23/2022 Partial Approval SABAS ALONSO
Underground Mechanical 6/23/2022 Corrections Issued SABAS ALONSO
PLUMBING-Rough 7/26/2022 Partial Approval SABAS ALONSO
PLUMBING-Rough 7/29/2022 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 9/1/2022 Partial Inspection MICHAEL LEWIS
ELECTRICAL-Rough 9/1/2022 Approved MICHAEL LEWIS
Green Building Rough 9/1/2022 Partial Inspection MICHAEL LEWIS
HVAC-Rough 9/1/2022 Partial Approval MICHAEL LEWIS
METHANE-Rough 9/1/2022 Approved MICHAEL LEWIS
PLUMBING-Rough 9/1/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/12/2022 Approved SABAS ALONSO
Green Building Rough 9/12/2022 Approved SABAS ALONSO
HVAC-Rough 9/12/2022 Approved SABAS ALONSO
Drywall Nailing 9/19/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 9/19/2022 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 9/20/2022 Approved SABAS ALONSO
Shower Pan 9/20/2022 Approved SABAS ALONSO
ELECTRICAL-Final 3/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 3/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 3/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 3/31/2023 Not Ready for Inspection SABAS ALONSO
Green Building Final 3/31/2023 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 3/31/2023 Approved SABAS ALONSO
ELECTRICAL-Final 4/12/2023 Not Ready for Inspection SABAS ALONSO
Final 4/12/2023 Not Ready for Inspection SABAS ALONSO
Green Building Final 4/12/2023 Not Ready for Inspection SABAS ALONSO
HVAC-Final 4/12/2023 Not Ready for Inspection SABAS ALONSO
PLUMBING-Final 4/12/2023 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/12/2023 SGSOV Approved SABAS ALONSO
ELECTRICAL-Final 4/17/2023 Approved SABAS ALONSO
Final 4/17/2023 Corrections Issued SABAS ALONSO
Green Building Final 4/17/2023 Approved SABAS ALONSO
HVAC-Final 4/17/2023 Approved SABAS ALONSO
PLUMBING-Final 4/17/2023 Approved SABAS ALONSO
Final 4/24/2023 Conditional Approval SABAS ALONSO
Final 6/20/2023 OK to Issue CofO SABAS ALONSO