523 N LAUREL AVE 90048
Certificate Information: 523 N LAUREL AVE 90048
- Application / Permit
- 21016-30000-20830
- Plan Check / Job No.
- B21WL03588
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convertion of existing detached garage to ADU per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/20/2021
- Issuing Office
- Current Status
- CofO Issued on 8/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2021 | MANUEL GARCIA |
| Corrections Issued | 8/14/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/16/2021 | JASON JANGADA |
| Plan Check Approved | 11/2/2021 | MANUEL GARCIA |
| Building Plans Picked Up | 11/3/2021 | APPLICANT |
| Issued | 12/20/2021 | APPLICANT |
| CofO in Progress | 8/15/2025 | JOSE MACIAS |
| Permit Finaled | 8/16/2025 | DEROLD HAUFF |
| Permit Finaled | 8/16/2025 | DEROLD HAUFF |
| CofO Issued | 8/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/21/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 8/21/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2021 | RENZ SORIANO |
| Address approval | Cleared | 8/25/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 10/21/2021 | ROBERT DUFF |
| Construction near power lines | Cleared | 10/25/2021 | RIDWAN HARDY |
Contact Information
| Contractor | D & J Optimum Development; Lic. No.: 1037421-B | 17844 HARTLAND ST RESEDA, CA 91335 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 1/19/2022 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 1/19/2022 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 2/2/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 2/8/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/29/2022 | Partial Approval | MICHAEL LEWIS |
| Green Building Rough | 9/29/2022 | Partial Inspection | MICHAEL LEWIS |
| Interior/Exterior Lathing | 9/29/2022 | Partial Approval | MICHAEL LEWIS |
| METHANE-Rough | 9/29/2022 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 2/17/2023 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 2/17/2023 | Corrections Issued | MICHAEL LEWIS |
| Underground Mechanical | 2/17/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 3/8/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 3/8/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 3/8/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/16/2023 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/4/2023 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Approved | LILIANA PORTILLO |
| Green Building Rough | 8/4/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Insulation | 6/6/2024 | Conditional Approval | AMIR NAZARIAN |
| Drywall Nailing | 6/11/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 6/28/2024 | Approved | AMIR NAZARIAN |
| Shower Pan | 6/28/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 4/29/2025 | Approved | JOSE MACIAS |
| Final | 4/29/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 4/29/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 4/29/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 4/29/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 5/19/2025 | Corrections Issued | JOSE MACIAS |
| Final | 5/19/2025 | Corrections Issued | JOSE MACIAS |
| HVAC-Final | 5/19/2025 | Approved | JOSE MACIAS |
| PLUMBING-Final | 5/19/2025 | Approved | JOSE MACIAS |
| Final | 5/20/2025 | Conditional Approval | JOSE MACIAS |
| Final | 5/23/2025 | Conditional Approval | JOSE MACIAS |
| Final | 8/15/2025 | OK to Issue CofO | JOSE MACIAS |