235 N AVENUE 51 90042
Certificate Information: 235 N AVENUE 51 90042
- Application / Permit
- 21016-30000-20506
- Plan Check / Job No.
- B21WL03544
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert portion of (e) S.F.D. to (n) ADU. PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/29/2021
- Issuing Office
- Current Status
- CofO Issued on 7/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2021 | ALFREDO JARA |
| Corrections Issued | 8/18/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 10/22/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 10/28/2021 | MANUEL GARCIA |
| Plan Check Approved | 11/16/2021 | MANUEL GARCIA |
| Issued | 11/29/2021 | APPLICANT |
| Building Plans Picked Up | 12/6/2021 | APPLICANT |
| CofO in Progress | 4/1/2022 | AMY COLIN |
| CofO in Progress | 7/6/2022 | AMY COLIN |
| CofO in Progress | 7/12/2022 | AMY COLIN |
| CofO Issued | 7/13/2022 | DEROLD HAUFF |
| Permit Finaled | 7/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 8/23/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | RENZ SORIANO |
| Specific Plan | Cleared | 8/25/2021 | MOHAMMAD HASAN |
| HPOZ | Cleared | 8/27/2021 | KATIE DEBIASE |
| ZI | Cleared | 8/27/2021 | KATIE DEBIASE |
| Specific Plan | Cleared | 8/31/2021 | ADRINEH MELKONIAN |
| Tenant Habitability Plan | Cleared | 10/5/2021 | MICHAEL SOTO |
| Hydrant and Access approval | Cleared | 10/10/2021 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/9/2021 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 1/21/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 1/21/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Rough | 1/27/2022 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 1/27/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/3/2022 | Corrections Issued | COREY HUPP |
| HVAC-Rough | 3/3/2022 | Not Ready for Inspection | COREY HUPP |
| Drywall Nailing | 3/18/2022 | Not Ready for Inspection | AMY COLIN |
| HVAC-Rough | 3/18/2022 | Not Ready for Inspection | AMY COLIN |
| Insulation | 3/18/2022 | Not Ready for Inspection | AMY COLIN |
| Drywall Nailing | 3/21/2022 | Approved | AMY COLIN |
| HVAC-Rough | 3/21/2022 | Approved | AMY COLIN |
| Insulation | 3/21/2022 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 3/31/2022 | Approved | AMY COLIN |
| ELECTRICAL-Final | 3/31/2022 | Approved | AMY COLIN |
| Final | 3/31/2022 | Partial Inspection | AMY COLIN |
| Gas Test | 3/31/2022 | Approved | AMY COLIN |
| HVAC-Final | 3/31/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 3/31/2022 | Approved | AMY COLIN |
| Smoke Detectors | 3/31/2022 | Approved | AMY COLIN |
| Final | 7/6/2022 | Corrections Issued | AMY COLIN |
| Final | 7/12/2022 | OK to Issue CofO | AMY COLIN |