7431 N DE SOTO AVE 91303

Certificate Information: 7431 N DE SOTO AVE 91303

Application / Permit
21016-30000-19858
Plan Check / Job No.
B21WL03427
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ADU conversion from (E) detached garage per WFPP, No sqft added. Per GCSc65852.2 (e)(1)(A)
Permit Issued
Issued on 4/1/2022
Issuing Office
Current Status
Issued on 4/1/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/19/2021 APPLICANT
Assigned to Plan Check Engineer 8/23/2021 KHUONG TRUONG
Corrections Issued 8/24/2021 KHUONG TRUONG
Applicant returned to address corrections 3/13/2022 ALFREDO JARA
Plan Check Approved 3/14/2022 ALFREDO JARA
Building Plans Picked Up 3/15/2022 APPLICANT
Issued 4/1/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/31/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/31/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 2/8/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 2/9/2022 RUEL COLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/8/2022 Approved TROY SANDERS
PLUMBING-Rough 4/8/2022 Partial Approval TROY SANDERS
ELECTRICAL-Rough 4/12/2022 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 4/12/2022 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 4/12/2022 Partial Approval DAVID SCANTLIN
Wood Frame 4/12/2022 Approved DAVID SCANTLIN
ELECTRICAL-Rough 4/13/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 4/13/2022 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 4/13/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 4/13/2022 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 4/13/2022 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 4/14/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/14/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 4/14/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 4/14/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/18/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 4/18/2022 Approved SEAN HAUPT
Insulation 4/18/2022 Approved SEAN HAUPT
Final 4/20/2022 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 4/20/2022 Approved STEVEN BACK
Sewer 4/20/2022 Approved STEVEN BACK
Final 5/5/2022 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/5/2022 SGSOV Not Ready STEVEN BACK
Smoke Detectors 5/5/2022 Approved STEVEN BACK
Drywall Nailing 5/13/2022 Approved STEVEN BACK
Final 5/13/2022 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/13/2022 SGSOV Approved STEVEN BACK