1575 1/2 N MUNSON AVE 90042

Certificate Information: 1575 1/2 N MUNSON AVE 90042

Application / Permit
21016-30000-19609
Plan Check / Job No.
B21WL03384
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to and conversion of (E) detached garage into a new ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 3/1/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 MANUEL GARCIA
Corrections Issued 8/5/2021 MANUEL GARCIA
Applicant returned to address corrections 1/30/2022 RICHARD GARCIA
Building Plans Picked Up 2/3/2022 APPLICANT
Applicant returned to address corrections 10/12/2022 JASON JANGADA
Applicant returned to address corrections 2/7/2023 EDWIN ESPIN
Plan Check Approved 2/10/2023 AMY GUEVARRA
Issued 3/1/2023 APPLICANT
CofO in Progress 3/17/2025 DAVID WILLIAMS
Permit Finaled 3/18/2025 DEROLD HAUFF
CofO Issued 3/18/2025 DEROLD HAUFF
Permit Finaled 3/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/23/2021 CECILIO NAVARRO
Sewer availability Cleared 8/23/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/24/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 10/19/2021 KURT CORRAL
Address approval Cleared 12/3/2021 WALLIE JONG
Construction near power lines Cleared 12/13/2021 RIDWAN HARDY
ZA Case Cleared 12/16/2021 RICHARD REASER
Grading Pre-Inspection Cleared 2/1/2022 MANUEL GARCIA
Tenant Habitability Plan Cleared 1/5/2023 MICHAEL SOTO
Low Impact Development Cleared 1/17/2023 CHRIS VONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/5/2023 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 4/5/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 4/5/2023 Not Ready for Inspection CRAIG VAUGHAN
Piling/Pier/Caisson 4/5/2023 Not Ready for Inspection CRAIG VAUGHAN
Pre-Inspection 4/5/2023 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Not Ready CRAIG VAUGHAN
Sewer 4/5/2023 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 7/3/2023 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 7/13/2023 Corrections Issued CRAIG VAUGHAN
Deputy Drilled-In Anchors 10/3/2023 Conditional Approval ROY SPAULDING
Footing/Foundation/Slab 10/10/2023 Approved ROY SPAULDING
PLUMBING-Rough 10/10/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 11/8/2023 Partial Approval ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Approved ROY SPAULDING
Green Building Rough 11/8/2023 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 12/1/2023 Partial Approval ROY SPAULDING
Interior/Exterior Lathing 2/14/2024 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 2/14/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/13/2024 Approved ALIZAH MAYAGOITIA
HVAC-Final 6/24/2024 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 6/26/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 6/26/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/2/2024 Approved ALIZAH MAYAGOITIA
Insulation 7/2/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 8/1/2024 Approved ANTHONY RAMOS
SGSOV-Seismic Gas S/O Valve 11/7/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
ELECTRICAL-Final 11/8/2024 Corrections Issued ALIZAH MAYAGOITIA
Final 11/20/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 11/20/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 11/20/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 11/20/2024 Approved ALIZAH MAYAGOITIA
Final 12/12/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 12/12/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/12/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/3/2025 Approved CRAIG DAVIS
Final 2/3/2025 Corrections Issued CRAIG DAVIS
Green Building Final 2/3/2025 Approved CRAIG DAVIS
Non Compliance 2/3/2025 Not Required CRAIG DAVIS
PLUMBING-Final 2/3/2025 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 2/3/2025 SGSOV Approved CRAIG DAVIS
Service/Power Release 2/3/2025 Approved CRAIG DAVIS
PLUMBING-Final 2/6/2025 Approved CRAIG DAVIS
Final 2/20/2025 Partial Approval CRAIG DAVIS
Final 3/12/2025 No Access for Inspection DAVID WILLIAMS
Final 3/14/2025 OK to Issue CofO DAVID WILLIAMS