1575 1/2 N MUNSON AVE 90042
Certificate Information: 1575 1/2 N MUNSON AVE 90042
- Application / Permit
- 21016-30000-19609
- Plan Check / Job No.
- B21WL03384
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to and conversion of (E) detached garage into a new ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 3/1/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | MANUEL GARCIA |
| Corrections Issued | 8/5/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 1/30/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 2/3/2022 | APPLICANT |
| Applicant returned to address corrections | 10/12/2022 | JASON JANGADA |
| Applicant returned to address corrections | 2/7/2023 | EDWIN ESPIN |
| Plan Check Approved | 2/10/2023 | AMY GUEVARRA |
| Issued | 3/1/2023 | APPLICANT |
| CofO in Progress | 3/17/2025 | DAVID WILLIAMS |
| Permit Finaled | 3/18/2025 | DEROLD HAUFF |
| CofO Issued | 3/18/2025 | DEROLD HAUFF |
| Permit Finaled | 3/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/23/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/23/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 10/19/2021 | KURT CORRAL |
| Address approval | Cleared | 12/3/2021 | WALLIE JONG |
| Construction near power lines | Cleared | 12/13/2021 | RIDWAN HARDY |
| ZA Case | Cleared | 12/16/2021 | RICHARD REASER |
| Grading Pre-Inspection | Cleared | 2/1/2022 | MANUEL GARCIA |
| Tenant Habitability Plan | Cleared | 1/5/2023 | MICHAEL SOTO |
| Low Impact Development | Cleared | 1/17/2023 | CHRIS VONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/5/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/5/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/5/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 4/5/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 4/5/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Sewer | 4/5/2023 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/3/2023 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 7/13/2023 | Corrections Issued | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 10/3/2023 | Conditional Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 10/10/2023 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 10/10/2023 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 11/8/2023 | Partial Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Approved | ROY SPAULDING |
| Green Building Rough | 11/8/2023 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 12/1/2023 | Partial Approval | ROY SPAULDING |
| Interior/Exterior Lathing | 2/14/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 2/14/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/13/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 6/24/2024 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/26/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 6/26/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/2/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 7/2/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 8/1/2024 | Approved | ANTHONY RAMOS |
| SGSOV-Seismic Gas S/O Valve | 11/7/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 11/8/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 11/20/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 11/20/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 11/20/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 11/20/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 12/12/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 12/12/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/12/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/3/2025 | Approved | CRAIG DAVIS |
| Final | 2/3/2025 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 2/3/2025 | Approved | CRAIG DAVIS |
| Non Compliance | 2/3/2025 | Not Required | CRAIG DAVIS |
| PLUMBING-Final | 2/3/2025 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Approved | CRAIG DAVIS |
| Service/Power Release | 2/3/2025 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 2/6/2025 | Approved | CRAIG DAVIS |
| Final | 2/20/2025 | Partial Approval | CRAIG DAVIS |
| Final | 3/12/2025 | No Access for Inspection | DAVID WILLIAMS |
| Final | 3/14/2025 | OK to Issue CofO | DAVID WILLIAMS |