1440 1/2 S STANLEY AVE 90019
Certificate Information: 1440 1/2 S STANLEY AVE 90019
- Application / Permit
- 21016-30000-18887
- Plan Check / Job No.
- B21WL03248
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert portion of (e) detached garage into (n) 330 sf ADU. PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/4/2022
- Issuing Office
- Current Status
- CofO Issued on 7/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2021 | ALFREDO JARA |
| Corrections Issued | 8/5/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 10/20/2021 | ALFREDO JARA |
| Plan Check Approved | 1/28/2022 | ALFREDO JARA |
| Issued | 2/4/2022 | APPLICANT |
| Building Plans Picked Up | 2/7/2022 | APPLICANT |
| CofO in Progress | 7/20/2024 | JOAQUIN GREENOUGH |
| CofO Issued | 7/22/2024 | DEROLD HAUFF |
| Permit Finaled | 7/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/8/2021 | JEANIE LAM |
| Sewer availability | Cleared | 9/8/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 12/3/2021 | GILBERT URREA |
| Construction near power lines | Cleared | 12/30/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 12/30/2021 | WALTER RAMIREZ |
Contact Information
| Architect | Holz,, Michael B; Lic. No.: C28082 | 12548 EVERGLADE STREET LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/11/2023 | Partial Approval | JOSE AVILA |
| Sewer | 4/18/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 4/18/2023 | Corrections Issued | MICHAEL LEWIS |
| Underground Mechanical | 4/24/2023 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/25/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 4/27/2023 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 6/1/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 6/5/2023 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 6/6/2023 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 6/13/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 8/10/2023 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 8/10/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 8/22/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/22/2023 | Approved | LILIANA PORTILLO |
| METHANE-Rough | 8/22/2023 | Approved | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 9/12/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/18/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | JOSE AVILA |
| Insulation | 10/25/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 10/25/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 11/6/2023 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/20/2023 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 11/20/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/12/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 7/12/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Smoke Detectors | 7/12/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 7/18/2024 | OK to Issue CofO | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 7/18/2024 | Approved | JOAQUIN GREENOUGH |