207 N SALTAIR AVE 90049
Certificate Information: 207 N SALTAIR AVE 90049
- Application / Permit
- 21016-30000-18786
- Plan Check / Job No.
- B21WL03232
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Foundation retrofit/repair & new shearwall for (E) 2-story S.F.D. Per engineering design.
- Permit Issued
- Issued on 12/3/2021
- Issuing Office
- Current Status
- Permit Finaled on 2/3/2022
Permit Application Status History
| Submitted | 7/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2021 | ALFREDO JARA |
| Corrections Issued | 7/28/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 11/5/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 11/19/2021 | ALFREDO JARA |
| Issued | 12/3/2021 | APPLICANT |
| Building Plans Picked Up | 12/7/2021 | APPLICANT |
| Permit Finaled | 2/3/2022 | CARLOS MATAMOROS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/10/2021 | ALFREDO JARA |
Contact Information
| Architect | Zellman,, Harold Alan; Lic. No.: C12968 | 553 MUSKINGUM PLACE PACIFIC PALISADES, CA 90272 |
| Contractor | Capper Construction; Lic. No.: 413563-B | 19222 KENYA STREET NORTHRIDGE, CA 91326 |
| Engineer | Mezey,, Steven William; Lic. No.: S2665 | 14017 HARTSOOK ST SHERMAN OAKS, CA 91423 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/16/2021 | Conditional Approval | KRISTEN CAUSEY |
| Deputy Drilled-In Anchors | 12/17/2021 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 12/17/2021 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/22/2021 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 12/22/2021 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 1/11/2022 | Approved | CARLOS MATAMOROS |
| Final | 1/31/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 1/31/2022 | Corrections Issued | CARLOS MATAMOROS |
| Final | 2/3/2022 | Permit Finaled | CARLOS MATAMOROS |