1143 S ALVIRA ST 90035
Certificate Information: 1143 S ALVIRA ST 90035
- Application / Permit
- 21016-30000-18320
- Plan Check / Job No.
- B21WL03147
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New wood deck and interior remodel at (E) SFD. Per engineering design.
- Permit Issued
- Issued on 9/10/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/30/2021
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2021 | KAVIAN REFAHI |
| Corrections Issued | 7/24/2021 | KAVIAN REFAHI |
| Plan Check Approved | 8/31/2021 | ALFREDO JARA |
| Issued | 9/10/2021 | APPLICANT |
| Permit Finaled | 12/29/2021 | JOSE AVILA |
Permit Application Clearance Information
| CPC | Cleared | 8/23/2021 | JONATHAN KAPLAN |
| HPOZ | Cleared | 8/23/2021 | JONATHAN KAPLAN |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/15/2021 | Not Ready for Inspection | CALEB MEISTER |
| Drywall Nailing | 9/15/2021 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 9/15/2021 | Corrections Issued | CALEB MEISTER |
| HVAC-Rough | 9/15/2021 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 9/15/2021 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Rough | 9/17/2021 | Approved | ALFREDO BALANDRA |
| PLUMBING-Rough | 9/17/2021 | Approved | ALFREDO BALANDRA |
| BUILDING-Rough-Frame | 9/21/2021 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 9/21/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 9/21/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/21/2021 | Order to Comply Issued | FREDDIE RIVERA |
| Shower Pan | 9/21/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/28/2021 | Partial Approval | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 9/28/2021 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 9/28/2021 | Approved | STUART CHAPMAN |
| HVAC-Rough | 9/28/2021 | Approved | STUART CHAPMAN |
| Insulation | 9/28/2021 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/30/2021 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/4/2021 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 10/6/2021 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 10/7/2021 | Approved | JUSTIN HAWLEY |
| Deputy Wood Construction | 10/12/2021 | Partial Approval | RUBEN SALAS |
| Interior/Exterior Lathing | 10/14/2021 | Partial Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 11/23/2021 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 11/30/2021 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 11/30/2021 | Approved | JOSE AVILA |
| Final | 12/22/2021 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/22/2021 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 12/22/2021 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 12/27/2021 | Approved | JOSE AVILA |
| Final | 12/29/2021 | Permit Finaled | JOSE AVILA |