650 E SUNSET AVE 90291

Certificate Information: 650 E SUNSET AVE 90291

Application / Permit
21016-30000-18026
Plan Check / Job No.
B21WL03085
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
Remodel to (E) garage + rec room. Rebuild and enclose stairs. Parking layout to change from 2 standard stalls to 1 standard and 1 compact stall.
Permit Issued
Issued on 5/10/2022
Issuing Office
Current Status
Permit Finaled on 9/23/2022

Permit Application Status History

Submitted 7/13/2021 APPLICANT
Assigned to Plan Check Engineer 7/20/2021 MANUEL GARCIA
Corrections Issued 7/21/2021 MANUEL GARCIA
Applicant returned to address corrections 12/22/2021 MANUEL GARCIA
Applicant returned to address corrections 2/26/2022 ALFREDO JARA
Plan Check Approved 5/2/2022 ALFREDO JARA
Issued 5/10/2022 APPLICANT
Building Plans Picked Up 5/13/2022 APPLICANT
Permit Finaled 9/23/2022 DAVID FEILER

Permit Application Clearance Information

Coastal Zone Cleared 11/30/2021 DALIA MOKAYED
Miscellaneous Cleared 11/30/2021 DALIA MOKAYED
Miscellaneous Cleared 11/30/2021 DALIA MOKAYED
Miscellaneous Cleared 11/30/2021 DALIA MOKAYED
Miscellaneous Cleared 11/30/2021 DALIA MOKAYED
Miscellaneous Cleared 11/30/2021 DALIA MOKAYED
ZA Case Cleared 11/30/2021 DALIA MOKAYED
Specific Plan Cleared 12/16/2021 IRA BROWN
ZA Case Cleared 3/30/2022 NOAH MCCOY
ZA Case Cleared 3/30/2022 NOAH MCCOY

Contact Information

Contractor Curb Appeal Construction; Lic. No.: 650380-B 5445 MEADOW VISTA WAY      AGOURA HILLS, CA 91301

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/18/2022 Conditional Approval JESUS RODRIGUEZ
Underground Mechanical 5/18/2022 Conditional Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 6/1/2022 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 6/27/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 7/21/2022 Partial Approval DAVID FEILER
ELECTRICAL-Rough 8/12/2022 Partial Approval DAVID FEILER
HVAC-Rough 8/12/2022 Approved DAVID FEILER
PLUMBING-Rough 8/12/2022 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 8/19/2022 Approved DAVID FEILER
Insulation 8/19/2022 Approved DAVID FEILER
Interior/Exterior Lathing 8/19/2022 Partial Approval DAVID FEILER
Rough-Elec/Plmb/HVAC 8/19/2022 Approved DAVID FEILER
Drywall Nailing 8/22/2022 Not Ready for Inspection DAVID FEILER
Drywall Nailing 8/24/2022 Approved DAVID FEILER
ELECTRICAL-Final 9/20/2022 Not Ready for Inspection DAVID FEILER
Final 9/20/2022 Corrections Issued DAVID FEILER
HVAC-Final 9/20/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 9/20/2022 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/20/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 9/20/2022 No Access for Inspection DAVID FEILER
ELECTRICAL-Final 9/22/2022 Partial Inspection DAVID FEILER
Final 9/22/2022 Not Ready for Inspection DAVID FEILER
HVAC-Final 9/22/2022 Partial Inspection DAVID FEILER
PLUMBING-Final 9/22/2022 Partial Inspection DAVID FEILER
Smoke Detectors 9/22/2022 Partial Approval DAVID FEILER
ELECTRICAL-Final 9/23/2022 Approved DAVID FEILER
Final 9/23/2022 Permit Finaled DAVID FEILER
Smoke Detectors 9/23/2022 Approved DAVID FEILER