14910 W SUNSET BLVD 90272

Certificate Information: 14910 W SUNSET BLVD 90272

Application / Permit
21016-30000-17143
Plan Check / Job No.
B21WL02941
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Structural remodel of (e) sfd. Convert the den into a new bedroom. Kitchen and bath remodel. Door and window changeout.
Permit Issued
Issued on 8/5/2021
Issuing Office
Current Status
Permit Finaled on 8/9/2022

Permit Application Status History

Submitted 7/1/2021 APPLICANT
Assigned to Plan Check Engineer 7/2/2021 RICHARD GARCIA
Corrections Issued 7/7/2021 RICHARD GARCIA
Applicant returned to address corrections 7/16/2021 RICHARD GARCIA
Plan Check Approved 7/29/2021 MANUEL GARCIA
Issued 8/5/2021 APPLICANT
Permit Finaled 8/8/2022 BRENDAN LOONEY

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/14/2021 CATHERINE ADROVER
Sewer availability Cleared 7/14/2021 CATHERINE ADROVER
Grading Pre-Inspection Cleared 7/15/2021 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/3/2021 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/13/2021 Approved ANDREW NAVE
Deputy Reinf. Concrete 9/14/2021 Conditional Approval ANDREW NAVE
Special/Order Compliance 9/23/2021 Partial Approval JESUS RODRIGUEZ
Wood Frame 9/23/2021 Partial Approval ANDREW NAVE
Deputy Steel/Welding 9/24/2021 Partial Approval ANDREW NAVE
PLUMBING-Rough 10/28/2021 Approved ANDREW NAVE
ELECTRICAL-Rough 10/29/2021 Partial Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Inspection ANDREW NAVE
ELECTRICAL-Rough 11/12/2021 Approved ANDREW NAVE
HVAC-Rough 11/12/2021 Approved ANDREW NAVE
Shower Pan 11/12/2021 Approved ANDREW NAVE
BUILDING-Rough-Frame 11/16/2021 Partial Approval ANDREW NAVE
Deputy Wood Construction 11/16/2021 Partial Approval ANDREW NAVE
Green Building Rough 11/16/2021 Partial Approval ANDREW NAVE
Drywall Nailing 11/22/2021 Approved DEANDRE HOFFMAN
Green Building Rough 11/22/2021 Approved DEANDRE HOFFMAN
Insulation 11/22/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 11/22/2021 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 5/12/2022 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 5/16/2022 Approved ANDREW NAVE
HVAC-Final 5/16/2022 Corrections Issued ANDREW NAVE
PLUMBING-Final 5/16/2022 Corrections Issued ANDREW NAVE
Final 8/1/2022 Not Ready for Inspection BRENDAN LOONEY
Green Building Final 8/1/2022 Approved BRENDAN LOONEY
HVAC-Final 8/1/2022 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 8/1/2022 Corrections Issued BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 8/1/2022 Approved BRENDAN LOONEY
Final 8/8/2022 Permit Finaled BRENDAN LOONEY