6040 W SUNSET BLVD 90028

Certificate Information: 6040 W SUNSET BLVD 90028

Application / Permit
21016-30000-16995
Plan Check / Job No.
B21WL02892
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Interior T.I. to 1st floor (5053 sf) of (e) 6-story office bldg. No change of use, occupancy or parking.
Permit Issued
Issued on 5/4/2022
Issuing Office
Metro
Current Status
Permit Finaled on 12/30/2022

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 REZA HAGHIGHAT
Corrections Issued 8/17/2021 REZA HAGHIGHAT
Quality Review Completed 8/30/2021 TARIK SAOUD
Building Plans Picked Up 1/18/2022 APPLICANT
Applicant returned to address corrections 1/20/2022 REZA HAGHIGHAT
Plan Check Approved 3/10/2022 REZA HAGHIGHAT
Issued 5/4/2022 APPLICANT
Permit Finaled 12/29/2022 RONALD JIMENEZ

Permit Application Clearance Information

ZI Cleared 9/24/2021 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 10/7/2021 GRACIELA ACOSTA
ZI Cleared 10/7/2021 GRACIELA ACOSTA
Green Code Cleared 1/14/2022 RICHARD GARCIA
DAS Clearance Cleared 1/19/2022 REZA HAGHIGHAT
Green Code Cleared 3/10/2022 REZA HAGHIGHAT

Contact Information

Architect Bolander,, William Bruce; Lic. No.: C29808 2710 LAS FLORES CANYON ROAD      MALIBU, CA 90265
Contractor Isis Commercial Interiors Inc; Lic. No.: 991155-B 865 S FIGUEROA STREET STE 3300      LOS ANGELES, CA 90017

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/13/2022 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 10/15/2022 Approved JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 10/17/2022 Approved JONATHAN QUACH
Footing/Foundation/Slab 10/17/2022 Approved JONATHAN QUACH
Deputy Drilled-In Anchors 10/27/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/27/2022 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 11/2/2022 Partial Approval JONATHAN QUACH
Deputy Drilled-In Anchors 11/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 11/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 11/22/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/22/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 11/29/2022 Partial Approval RONALD JIMENEZ
Deputy Reinf. Concrete 11/29/2022 Partial Approval RONALD JIMENEZ
Deputy Fireproofing 12/2/2022 Conditional Approval MICHAEL ROSENBERG
Final 12/29/2022 Permit Finaled RONALD JIMENEZ
Green Building Final 12/29/2022 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 12/29/2022 Approved RONALD JIMENEZ