6040 W SUNSET BLVD 90028
Certificate Information: 6040 W SUNSET BLVD 90028
- Application / Permit
- 21016-30000-16995
- Plan Check / Job No.
- B21WL02892
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Interior T.I. to 1st floor (5053 sf) of (e) 6-story office bldg. No change of use, occupancy or parking.
- Permit Issued
- Issued on 5/4/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/30/2022
Permit Application Status History
| Submitted | 7/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | REZA HAGHIGHAT |
| Corrections Issued | 8/17/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 8/30/2021 | TARIK SAOUD |
| Building Plans Picked Up | 1/18/2022 | APPLICANT |
| Applicant returned to address corrections | 1/20/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 3/10/2022 | REZA HAGHIGHAT |
| Issued | 5/4/2022 | APPLICANT |
| Permit Finaled | 12/29/2022 | RONALD JIMENEZ |
Permit Application Clearance Information
| ZI | Cleared | 9/24/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 10/7/2021 | GRACIELA ACOSTA |
| ZI | Cleared | 10/7/2021 | GRACIELA ACOSTA |
| Green Code | Cleared | 1/14/2022 | RICHARD GARCIA |
| DAS Clearance | Cleared | 1/19/2022 | REZA HAGHIGHAT |
| Green Code | Cleared | 3/10/2022 | REZA HAGHIGHAT |
Contact Information
| Architect | Bolander,, William Bruce; Lic. No.: C29808 | 2710 LAS FLORES CANYON ROAD MALIBU, CA 90265 |
| Contractor | Isis Commercial Interiors Inc; Lic. No.: 991155-B | 865 S FIGUEROA STREET STE 3300 LOS ANGELES, CA 90017 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/13/2022 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 10/15/2022 | Approved | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 10/17/2022 | Approved | JONATHAN QUACH |
| Footing/Foundation/Slab | 10/17/2022 | Approved | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 10/27/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 10/27/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Light Gage Steel Frame | 11/2/2022 | Partial Approval | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 11/21/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Fireproofing | 11/21/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 11/21/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 11/22/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 11/22/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 11/29/2022 | Partial Approval | RONALD JIMENEZ |
| Deputy Reinf. Concrete | 11/29/2022 | Partial Approval | RONALD JIMENEZ |
| Deputy Fireproofing | 12/2/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Final | 12/29/2022 | Permit Finaled | RONALD JIMENEZ |
| Green Building Final | 12/29/2022 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 12/29/2022 | Approved | RONALD JIMENEZ |