1447 S SPAULDING AVE 90019
Certificate Information: 1447 S SPAULDING AVE 90019
- Application / Permit
- 21016-30000-16399
- Plan Check / Job No.
- B21WL02805
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Converting existing garage into an accessory dwelling unit per engineer's design per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- Issued on 4/26/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2021 | JASON JANGADA |
| Corrections Issued | 7/3/2021 | JASON JANGADA |
| Applicant returned to address corrections | 2/7/2022 | EDWIN ESPIN |
| Plan Check Approved | 2/7/2022 | EDWIN ESPIN |
| Issued | 4/26/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/7/2021 | WALLIE JONG |
| Sewer availability | Cleared | 9/7/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 1/4/2022 | RUEL COLE |
Contact Information
| Contractor | Manasse Inc; Lic. No.: 607634-B | 29059 RAINTREE LN SAUGUS, CA 91390 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/2/2022 | Partial Approval | JOSE AVILA |
| Underground Mechanical | 6/14/2022 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 6/23/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 11/17/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 11/17/2022 | Approved | JOSE AVILA |
| METHANE-Rough | 11/17/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 11/17/2022 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 11/17/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/27/2022 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 12/27/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 12/27/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Partial Approval | MICHAEL LEWIS |
| Insulation | 1/4/2023 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/9/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 1/13/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 1/24/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 2/4/2023 | Approved | DONALD CRICHLOW |
| Interior/Exterior Lathing | 2/7/2023 | Approved | DONALD CRICHLOW |
| Final | 9/26/2023 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 9/26/2023 | Approved | JOSE AVILA |
| Final | 11/2/2023 | Corrections Issued | JOSE AVILA |