652 1/2 N DILLON ST 90026
Certificate Information: 652 1/2 N DILLON ST 90026
- Application / Permit
- 21016-30000-16121
- Plan Check / Job No.
- B21WL02748
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) garage to Attached ADU unit per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 1/11/2022
- Issuing Office
- Current Status
- CofO Issued on 9/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | JASON JANGADA |
| Corrections Issued | 6/26/2021 | JASON JANGADA |
| Applicant returned to address corrections | 10/14/2021 | KHUONG TRUONG |
| Applicant returned to address corrections | 11/9/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 11/23/2021 | MARJAN SHENASI |
| Building Plans Picked Up | 12/1/2021 | APPLICANT |
| Plan Check Approved | 1/4/2022 | MARJAN SHENASI |
| Issued | 1/11/2022 | APPLICANT |
| CofO in Progress | 6/6/2023 | FREDDIE RIVERA |
| CofO Issued | 9/25/2023 | DEROLD HAUFF |
| Permit Finaled | 9/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/21/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2021 | THOMAS LANG |
| Sewer availability | Cleared | 7/21/2021 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 9/10/2021 | MATTHEW CRAIG |
| Tenant Habitability Plan | Cleared | 10/6/2021 | RICHARD BRINSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/8/2022 | Corrections Issued | ADAM ESCOTO |
| PLUMBING-Rough | 3/8/2022 | Corrections Issued | ADAM ESCOTO |
| BUILDING-Rough-Frame | 3/23/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 3/23/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| METHANE-Rough | 3/23/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/24/2022 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 8/24/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/7/2022 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/7/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 9/7/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 9/7/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/8/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 9/8/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 9/8/2022 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 9/8/2022 | Approved | FREDDIE RIVERA |
| Insulation | 9/20/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 9/22/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 11/10/2022 | Partial Inspection | FREDDIE RIVERA |
| Final | 11/10/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 11/10/2022 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 11/10/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 11/10/2022 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 11/10/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 11/17/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 11/17/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/17/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 12/5/2022 | Partial Inspection | FREDDIE RIVERA |
| Final | 12/5/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 12/5/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 12/5/2022 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 12/5/2022 | SGSOV Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 1/11/2023 | No Access for Inspection | FREDDIE RIVERA |
| Final | 1/11/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 1/11/2023 | No Access for Inspection | FREDDIE RIVERA |
| HVAC-Final | 1/11/2023 | No Access for Inspection | FREDDIE RIVERA |
| Final | 1/13/2023 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 1/13/2023 | Approved | FREDDIE RIVERA |
| Final | 6/6/2023 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 6/6/2023 | Approved | FREDDIE RIVERA |