7429 S WESTLAWN AVE 90045

Certificate Information: 7429 S WESTLAWN AVE 90045

Application / Permit
21016-30000-15777
Plan Check / Job No.
B21WL02691
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) garage to ADU per CA G.C.S. 65852.2(e)(1)(A) at rear of the lot.
Permit Issued
Issued on 1/19/2022
Issuing Office
Current Status
CofO Issued on 5/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 KAVIAN REFAHI
Corrections Issued 6/26/2021 KAVIAN REFAHI
Applicant returned to address corrections 10/5/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 10/21/2021 MARJAN SHENASI
Applicant returned to address corrections 11/9/2021 MANUEL GARCIA
Applicant returned to address corrections 12/2/2021 JAHANSHAH POURHASSAN
Building Plans Picked Up 12/3/2021 APPLICANT
Plan Check Approved 12/21/2021 JAHANSHAH POURHASSAN
Issued 1/19/2022 APPLICANT
CofO in Progress 3/7/2023 ANDREW BEELI
Permit Finaled 5/3/2023 BRUCE TODD
CofO Issued 5/3/2023 BRUCE TODD
Permit Finaled 5/3/2023 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 7/13/2021 DINAH GARIN
Sewer availability Cleared 7/13/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/15/2021 DINAH GARIN
Hydrant and Access approval Cleared 9/4/2021 RUEL COLE
Grading Pre-Inspection Cleared 10/5/2021 KAVIAN REFAHI
Construction near power lines Cleared 10/18/2021 TORI CHEN

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/21/2022 Partial Approval JOHN MATTILLO
ELECTRICAL-Rough 5/12/2022 Corrections Issued MARIAN PODPORA
HVAC-Rough 5/12/2022 Corrections Issued MARIAN PODPORA
PLUMBING-Rough 5/12/2022 Corrections Issued MARIAN PODPORA
Wood Frame 5/12/2022 Corrections Issued MARIAN PODPORA
BUILDING-Rough-Frame 5/17/2022 Not Ready for Inspection MARIAN PODPORA
Deputy Drilled-In Anchors 5/17/2022 Approved MARIAN PODPORA
ELECTRICAL-Rough 5/17/2022 Partial Approval MARIAN PODPORA
Green Building Rough 5/17/2022 Not Ready for Inspection MARIAN PODPORA
HVAC-Rough 5/17/2022 Partial Approval MARIAN PODPORA
METHANE-Rough 5/17/2022 Not Ready for Inspection MARIAN PODPORA
PLUMBING-Rough 5/17/2022 Partial Approval MARIAN PODPORA
Footing/Foundation/Slab 5/23/2022 Partial Approval JOHN MATTILLO
BUILDING-Rough-Frame 5/25/2022 Not Ready for Inspection MARIAN PODPORA
Green Building Rough 5/25/2022 Not Ready for Inspection MARIAN PODPORA
Insulation 5/25/2022 Not Ready for Inspection MARIAN PODPORA
METHANE-Rough 5/25/2022 Not Ready for Inspection MARIAN PODPORA
BUILDING-Rough-Frame 5/31/2022 Partial Approval MARIAN PODPORA
Green Building Rough 5/31/2022 Not Ready for Inspection MARIAN PODPORA
Insulation 5/31/2022 Not Ready for Inspection MARIAN PODPORA
METHANE-Rough 5/31/2022 Approved MARIAN PODPORA
Insulation 6/1/2022 Approved MARIAN PODPORA
Wood Frame 6/1/2022 Partial Approval MARIAN PODPORA
Drywall Nailing 6/6/2022 Corrections Issued JOHN MATTILLO
Interior/Exterior Lathing 6/6/2022 Partial Approval JOHN MATTILLO
Shower Pan 6/6/2022 Approved JOHN MATTILLO
Drywall Nailing 6/7/2022 Approved JOHN MATTILLO
Interior/Exterior Lathing 6/22/2022 Not Ready for Inspection MARIAN PODPORA
Interior/Exterior Lathing 6/23/2022 Corrections Issued MARIAN PODPORA
Interior/Exterior Lathing 6/24/2022 Partial Approval MARIAN PODPORA
PLUMBING-Rough 7/20/2022 Not Ready for Inspection JOHN MATTILLO
PLUMBING-Final 12/9/2022 Corrections Issued MARIAN PODPORA
BUILDING-Rough-Frame 1/19/2023 Approved MARIAN PODPORA
ELECTRICAL-Final 1/19/2023 Corrections Issued MARIAN PODPORA
Final 1/19/2023 Not Ready for Inspection MARIAN PODPORA
Green Building Final 1/19/2023 Approved MARIAN PODPORA
Green Building Rough 1/19/2023 Approved MARIAN PODPORA
HVAC-Final 1/19/2023 Corrections Issued MARIAN PODPORA
PLUMBING-Final 1/19/2023 Corrections Issued MARIAN PODPORA
SGSOV-Seismic Gas S/O Valve 1/19/2023 SGSOV Not Ready MARIAN PODPORA
Smoke Detectors 1/19/2023 Approved MARIAN PODPORA
ELECTRICAL-Rough 2/14/2023 Not Ready for Inspection ANDREW BEELI
Final 2/14/2023 Corrections Issued ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Not Ready ANDREW BEELI
Final 2/17/2023 Not Ready for Inspection ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 2/17/2023 SGSOV Not Ready ANDREW BEELI
Final 3/6/2023 Not Ready for Inspection ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 3/6/2023 SGSOV Approved ANDREW BEELI
ELECTRICAL-Final 3/7/2023 Approved ANDREW BEELI
ELECTRICAL-Rough 3/7/2023 Approved ANDREW BEELI
Final 3/7/2023 OK to Issue CofO ANDREW BEELI
HVAC-Final 3/7/2023 Approved ANDREW BEELI
PLUMBING-Final 3/7/2023 Approved ANDREW BEELI
PLUMBING-Rough 3/7/2023 Approved ANDREW BEELI