2470 N GLENDOWER PL 90027
Certificate Information: 2470 N GLENDOWER PL 90027
- Application / Permit
- 21016-30000-15719
- Plan Check / Job No.
- B21WL02686
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached rec. room to ADU (547sqft) PER GCS 65852.2(E)(1)(A)
- Permit Issued
- Issued on 10/5/2021
- Issuing Office
- Current Status
- Issued on 10/5/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | KHUONG TRUONG |
| Corrections Issued | 6/26/2021 | KHUONG TRUONG |
| Plan Check Approved | 9/24/2021 | ALFREDO JARA |
| Issued | 10/5/2021 | APPLICANT |
| Building Plans Picked Up | 10/7/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2021 | STEVE MELGAR |
| Address approval | Cleared | 8/4/2021 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 9/11/2021 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Letz, Damon Leroy; Lic. No.: C40872 | 28209 STONINGTON LANE SAUGUS, CA 91350 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/12/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/12/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/12/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/20/2021 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/20/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 10/20/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/20/2021 | Approved | JOSEPH MCGARRY |
| Pre-Inspection | 10/22/2021 | Approved | JOSEPH MCGARRY |
| Shower Pan | 3/31/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/4/2022 | Approved | JOSEPH MCGARRY |
| Final | 6/4/2026 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 6/4/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 6/4/2026 | Not Ready for Inspection | ENRIQUE MIRELES |