5000 W 63RD ST 90056

Certificate Information: 5000 W 63RD ST 90056

Application / Permit
21016-30000-15438
Plan Check / Job No.
B21WL02605
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel remove wall between kichen and dining room, bathroom remodel, move existing closet to accomodate shower. Per engineering design.
Permit Issued
Issued on 10/19/2021
Issuing Office
Current Status
Permit Finaled on 3/3/2022

Permit Application Status History

Submitted 6/20/2021 APPLICANT
Assigned to Plan Check Engineer 6/21/2021 ALFREDO JARA
Corrections Issued 6/22/2021 ALFREDO JARA
Applicant returned to address corrections 7/28/2021 ALFREDO JARA
Applicant returned to address corrections 8/9/2021 ALFREDO JARA
Plan Check Approved 9/10/2021 ALFREDO JARA
Issued 10/19/2021 APPLICANT
Permit Finaled 3/3/2022 CLAYTON GRAHAM

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/27/2021 PATRICK MISCHLICH

Contact Information

Contractor Harvey Ralph Donell; Lic. No.: 652651-B 11715 SOUTH WILTON PLACE      HAWTHORNE, CA 90250
Engineer Ayroso,, Ananias Maniquis; Lic. No.: S2413 12823 BERKHAMSTED ST      CERRITOS, CA 90703

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/25/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 10/28/2021 Corrections Issued BOBBY KEY
Pre-Inspection 10/28/2021 Partial Inspection DAVID FEILER
Footing/Foundation/Slab 11/1/2021 Approved BOBBY KEY
BUILDING-Rough-Frame 12/2/2021 Approved BOBBY KEY
ELECTRICAL-Rough 12/2/2021 Approved BOBBY KEY
PLUMBING-Rough 12/2/2021 Approved BOBBY KEY
Drywall Nailing 12/8/2021 Approved BOBBY KEY
ELECTRICAL-Final 12/8/2021 Corrections Issued BOBBY KEY
ELECTRICAL-Final 3/2/2022 Approved BOBBY KEY
Final 3/2/2022 Corrections Issued BOBBY KEY
Gas Test 3/2/2022 Approved BOBBY KEY
HVAC-Final 3/2/2022 Approved BOBBY KEY
PLUMBING-Final 3/2/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Not Ready BOBBY KEY
Smoke Detectors 3/2/2022 Approved BOBBY KEY
Final 3/3/2022 Permit Finaled CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Approved CLAYTON GRAHAM