942 N OLANCHA DR 90065
Certificate Information: 942 N OLANCHA DR 90065
- Application / Permit
- 21016-30000-14272
- Plan Check / Job No.
- B21WL02433
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel to convert family room to bedroom, add laundry area and convert one bathroom to 2 bathrooms.
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 11/2/2021
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2021 | ALFREDO JARA |
| Corrections Issued | 6/11/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 7/3/2021 | ALFREDO JARA |
| Plan Check Approved | 7/8/2021 | ALFREDO JARA |
| Issued | 7/20/2021 | APPLICANT |
| Permit Finaled | 11/1/2021 | HAMIK HARTOUNIAN |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/21/2021 | DYLAN LAWRENCE |
| Sewer availability | Cleared | 6/22/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2021 | CELINA MORENO |
Contact Information
| Contractor | Advanced General Construction; Lic. No.: 951083-B | 6545 HAZELTINE AVE # 212 VAN NUYS, CA 91401 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/23/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/23/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 8/23/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 8/26/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/7/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 10/25/2021 | Not Ready for Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 10/25/2021 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 10/25/2021 | Approved | JOSE AVILA |
| Final | 11/1/2021 | Permit Finaled | HAMIK HARTOUNIAN |