1114 S HOLT AVE 90035
Certificate Information: 1114 S HOLT AVE 90035
- Application / Permit
- 21016-30000-14113
- Plan Check / Job No.
- B21WL02397
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- convert existing garage to ADU Per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/11/2021
- Issuing Office
- Current Status
- CofO Issued on 4/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | KHUONG TRUONG |
| Corrections Issued | 6/5/2021 | KHUONG TRUONG |
| Applicant returned to address corrections | 10/6/2021 | KHUONG TRUONG |
| Plan Check Approved | 10/14/2021 | KHUONG TRUONG |
| Issued | 11/11/2021 | APPLICANT |
| Building Plans Picked Up | 11/15/2021 | APPLICANT |
| CofO in Progress | 4/1/2025 | EVAN COOPER |
| CofO Issued | 4/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 6/24/2021 | RENZ SORIANO |
| Construction near power lines | Cleared | 8/31/2021 | RIDWAN HARDY |
| "Q" conditions | Cleared | 9/9/2021 | KENTON TRINH |
| Hydrant and Access approval | Cleared | 9/9/2021 | GILBERT URREA |
| Tenant Habitability Plan | Cleared | 10/7/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Zakaria & Associates; Lic. No.: 768824-B | 838 S WOOSTER STREET LOS ANGELES, CA 90035 |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/17/2021 | Approved | JOHNNY MIRANDA |
| Pre-Inspection | 11/23/2021 | Approved | EVAN COOPER |
| Pre-Inspection | 1/4/2023 | Partial Inspection | JEREMY TODD |
| Special/Order Compliance | 1/4/2023 | Partial Inspection | MICHAEL PELHAM |
| Deputy Methane Barrier | 2/7/2023 | No Access for Inspection | JEREMY TODD |
| Footing/Foundation/Slab | 2/10/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/10/2023 | Partial Approval | JESUS RODRIGUEZ |
| Sewer | 2/10/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/10/2023 | Approved | ARAM AVEDISIAN |
| Final | 8/10/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 8/10/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 8/10/2023 | Approved | ARAM AVEDISIAN |
| METHANE-Final | 8/10/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| METHANE-Rough | 8/10/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 8/10/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/27/2025 | Approved | EVAN COOPER |
| Final | 3/27/2025 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 3/27/2025 | Approved | EVAN COOPER |
| METHANE-Final | 3/27/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 3/27/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/27/2025 | SGSOV Approved | EVAN COOPER |
| Final | 4/1/2025 | OK to Issue CofO | EVAN COOPER |