1135 S SHENANDOAH ST 90035
Certificate Information: 1135 S SHENANDOAH ST 90035
- Application / Permit
- 21016-30000-13885
- Plan Check / Job No.
- B21WL02348
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Structural repair to existing podium deck.
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- Issued on 1/12/2022
Permit Application Status History
| Submitted | 8/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | VLADIMIR ARUTYUNYAN |
| Disabled Access Plans Picked Up | 9/16/2021 | APPLICANT |
| Corrections Issued | 10/14/2021 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 10/25/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 12/17/2021 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 12/28/2021 | APPLICANT |
| Plan Check Approved | 1/12/2022 | REZA HAGHIGHAT |
| Issued | 1/12/2022 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 12/23/2021 | RICHARD GARCIA |
| DAS Clearance | Cleared | 1/3/2022 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Bel Esprit Builders Inc; Lic. No.: 709903-B | 23112 ALCALDE DR SUITE A LAGUNA HILLS, CA 92653 |
| Engineer | De, Vita, Vincent; Lic. No.: S4484 | 31202 BROOKS ST LAGUNA BEACH, CA 92651 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/31/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Pre-Inspection | 1/31/2022 | Approved | PAUL DAVIDSON |
| Reinforced Concrete Frame | 1/31/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Structural Steel Frame | 1/31/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Wall Anchors | 1/31/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Reinforced Concrete Frame | 2/2/2022 | Approved | PAUL DAVIDSON |
| Wall Anchors | 2/2/2022 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 2/14/2022 | Partial Inspection | PAUL DAVIDSON |
| Wood Frame | 2/17/2022 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 2/18/2022 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 2/23/2022 | Approved | PAUL DAVIDSON |
| Final | 5/18/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Green Building Final | 5/18/2022 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 5/18/2022 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 5/18/2022 | Approved | PAUL DAVIDSON |