528-530 E WESTMINSTER AVE 90291

Certificate Information: 528-530 E WESTMINSTER AVE 90291

Application / Permit
21016-30000-13650
Plan Check / Job No.
B21WL02277
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Interior & exterior remodel, and small covered patio to an existing 2-story duplex
Permit Issued
Issued on 1/7/2022
Issuing Office
Current Status
CofO Issued on 7/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2021 APPLICANT
Assigned to Plan Check Engineer 6/25/2021 FELIPE HERNANDEZ
Corrections Issued 7/2/2021 FELIPE HERNANDEZ
Quality Review Completed 7/12/2021 KAVIAN REFAHI
Plan Check Approved 11/5/2021 FELIPE HERNANDEZ
Building Plans Picked Up 11/9/2021 APPLICANT
Issued 1/7/2022 APPLICANT
CofO in Progress 6/26/2025 JESUS RODRIGUEZ
CofO in Progress 7/2/2025 DAVID FEILER
Permit Finaled 7/7/2025 RICHARD STEINBACH
CofO Issued 7/7/2025 RICHARD STEINBACH
Permit Finaled 7/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/27/2021 TRACY TATE
Tenant Habitability Plan Cleared 8/12/2021 RICARDO BOHORQUEZ
Trees in Parkway Cleared 8/12/2021 JOHN KIM
Specific Plan Cleared 8/13/2021 BINDU KANNAN
Roof/Waste drainage to street Cleared 8/31/2021 TRACY TATE
Coastal Zone Cleared 10/22/2021 LAUREN PADICK

Contact Information

Architect Osuch,, Edward M; Lic. No.: C32544 6191 ST ALBANS STREET # A      LOS ANGELES, CA 90042
Contractor Kara Construction Group Inc; Lic. No.: 1064239-B 347 W GARFIELD AVE      GLENDALE, CA 91204
Engineer Kang,, Danniel; Lic. No.: S6242 18411 CRENSHAW BLVD   SUITE 408    TORRANCE, CA 90504

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/28/2022 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/4/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 5/4/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 5/10/2023 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 5/30/2023 Partial Approval EVAN COOPER
Footing/Foundation/Slab 5/30/2023 Corrections Issued EVAN COOPER
METHANE-Rough 5/30/2023 Approved EVAN COOPER
PLUMBING-Rough 5/30/2023 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 8/10/2023 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 8/10/2023 Corrections Issued EVAN COOPER
Gas Test 8/10/2023 Partial Approval EVAN COOPER
PLUMBING-Rough 8/10/2023 Partial Approval EVAN COOPER
Sewer 8/10/2023 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/2/2024 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 2/2/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 2/2/2024 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 2/2/2024 Approved HERBERT GIRON
Sewer 2/2/2024 Not Ready for Inspection HERBERT GIRON
Deputy Reinf. Concrete 2/14/2024 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 3/18/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Approved HERBERT GIRON
Footing/Foundation/Slab 3/18/2024 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 3/21/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 4/1/2024 Approved HERBERT GIRON
Shower Pan 4/1/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 5/2/2024 Approved HERBERT GIRON
Shower Pan 5/2/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 5/7/2024 Approved HERBERT GIRON
Final 5/7/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 5/7/2024 Approved HERBERT GIRON
Green Building Rough 5/7/2024 Approved HERBERT GIRON
Verify Sprinkler Sign Off 5/7/2024 Approved HERBERT GIRON
Wood Frame 5/7/2024 Approved HERBERT GIRON
Insulation 5/21/2024 Partial Approval HERBERT GIRON
Insulation 5/23/2024 Approved HERBERT GIRON
Light Gage Steel Frame 5/23/2024 Approved HERBERT GIRON
Drywall Nailing 6/3/2024 Approved HERBERT GIRON
ELECTRICAL-Final 2/20/2025 Corrections Issued HERBERT GIRON
HVAC-Final 2/20/2025 Approved HERBERT GIRON
ELECTRICAL-Final 2/24/2025 Approved HERBERT GIRON
Gas Test 2/24/2025 Approved HERBERT GIRON
PLUMBING-Final 2/24/2025 Approved HERBERT GIRON
Service/Power Release 4/18/2025 Approved JESUS RODRIGUEZ
Final 6/10/2025 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 6/10/2025 No Access for Inspection JESUS RODRIGUEZ
Final 6/17/2025 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/17/2025 SGSOV Approved BOBBY KEY
Smoke Detectors 6/17/2025 Approved BOBBY KEY
Final 6/25/2025 OK to Issue CofO JESUS RODRIGUEZ