850 W COEUR D'ALENE AVE 90291
Certificate Information: 850 W COEUR D'ALENE AVE 90291
- Application / Permit
- 21016-30000-13547
- Plan Check / Job No.
- B21WL02254
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- RELOCATE ENTRY DOOR TO THE REAR YARD AND KITCHEN & BATHROOM REMODEL IN (E) DUPLEX
- Permit Issued
- Issued on 8/25/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/8/2022
Permit Application Status History
| Submitted | 5/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | JASON JANGADA |
| Corrections Issued | 5/27/2021 | JASON JANGADA |
| Applicant returned to address corrections | 8/5/2021 | MANUEL GARCIA |
| Plan Check Approved | 8/16/2021 | MANUEL GARCIA |
| Issued | 8/25/2021 | APPLICANT |
| Permit Finaled | 8/8/2022 | STEPHANIE SWANSON |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/11/2021 | BINDU KANNAN |
| ZI | Cleared | 6/11/2021 | BINDU KANNAN |
| Tenant Habitability Plan | Cleared | 6/14/2021 | RICARDO BOHORQUEZ |
| Coastal Zone | Cleared | 7/29/2021 | TERRI OSBORNE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 9/16/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 9/16/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/16/2021 | Corrections Issued | ENRIQUE MIRELES |
| Wood Frame | 9/16/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/14/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/14/2021 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/19/2021 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 2/17/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 2/28/2022 | Not Ready for Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 3/1/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 3/4/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 3/9/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 3/9/2022 | Partial Approval | DAVID FEILER |
| Interior/Exterior Lathing | 3/21/2022 | Conditional Approval | STEPHANIE SWANSON |
| Shower Pan | 3/21/2022 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 3/22/2022 | Approved | PATRICK QUALEY |
| ELECTRICAL-Final | 7/18/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 7/18/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 7/18/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 7/28/2022 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Final | 7/28/2022 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 7/28/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/8/2022 | Approved | STEPHANIE SWANSON |
| Final | 8/8/2022 | Permit Finaled | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 8/8/2022 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 8/8/2022 | Approved | STEPHANIE SWANSON |