2235 N GLOAMING WAY 90210

Certificate Information: 2235 N GLOAMING WAY 90210

Application / Permit
21016-30000-13532
Plan Check / Job No.
B21WL02248
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR AND EXTERIOR STRUCTURAL REMODEL. REPAIR OF WATER DAMAGED WALL AT TWO CARPORTS AND COURTYARD. REPLACE ROTTED FRAMING TIMBER WITH SAME SIZE TIMBER. APPLY (N) STUCCO SYSTEM AFTER FRAMING IS REPLACED. REPAIR SUPPORT TO ONE 9 FOOT WALL. NO NEW SF. KITCHEN AND BATH REMODEL.
Permit Issued
Issued on 6/29/2021
Issuing Office
Current Status
Permit Finaled on 3/23/2022

Permit Application Status History

Submitted 5/26/2021 APPLICANT
Assigned to Plan Check Engineer 5/27/2021 RICHARD GARCIA
Corrections Issued 5/31/2021 RICHARD GARCIA
Plan Check Approved 6/19/2021 RICHARD GARCIA
Issued 6/29/2021 APPLICANT
Permit Finaled 3/22/2022 ARTHUR SARGSYAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor R L D Homes Inc; Lic. No.: 760588-B 2138 PELHAM AVE      LOS ANGELES, CA 90025
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/14/2021 Approved RICHARD STEINBACH
PLUMBING-Rough 7/14/2021 Approved RICHARD STEINBACH
Deputy Drilled-In Anchors 7/29/2021 Conditional Approval RICHARD STEINBACH
Deputy Wood Construction 7/29/2021 Conditional Approval RICHARD STEINBACH
Wood Frame 7/29/2021 Partial Approval RICHARD STEINBACH
Deputy Drilled-In Anchors 8/5/2021 Conditional Approval RICHARD STEINBACH
ELECTRICAL-Rough 8/6/2021 Approved RAUL BARAJAS
PLUMBING-Rough 8/6/2021 Approved RAUL BARAJAS
Wood Frame 8/6/2021 Approved RAUL BARAJAS
Insulation 8/16/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 8/16/2021 Approved RAUL BARAJAS
Drywall Nailing 8/24/2021 Approved RICHARD STEINBACH
Interior/Exterior Lathing 8/24/2021 Approved RICHARD STEINBACH
Shower Pan 8/24/2021 Approved RICHARD STEINBACH
Final 3/22/2022 Permit Finaled ARTHUR SARGSYAN
Green Building Final 3/22/2022 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 3/22/2022 Approved ARTHUR SARGSYAN