1225 S MULLEN AVE 90019
Certificate Information: 1225 S MULLEN AVE 90019
- Application / Permit
- 21016-30000-13513
- Plan Check / Job No.
- B21WL02247
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SFD. CONVERTING AN (E) LAUNDRY ROOM/CLOSET INTO A MASTER BATHROOM. NEW PANTRY. RELOCATE WASHER/DRYER.
- Permit Issued
- Issued on 11/8/2021
- Issuing Office
- Current Status
- Permit Finaled on 2/3/2022
Permit Application Status History
| Submitted | 5/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2021 | RICHARD GARCIA |
| Corrections Issued | 6/3/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 6/30/2021 | JASON JANGADA |
| Plan Check Approved | 8/10/2021 | SERGIO SILVA |
| Issued | 11/8/2021 | APPLICANT |
| Building Plans Picked Up | 11/9/2021 | APPLICANT |
| Permit Finaled | 2/2/2022 | STUART CHAPMAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 11/17/2021 | Approved | STUART CHAPMAN |
| Gas Test | 11/17/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 11/17/2021 | Approved | STUART CHAPMAN |
| Wood Frame | 11/17/2021 | Approved | STUART CHAPMAN |
| Insulation | 11/19/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/19/2021 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 11/23/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/23/2021 | Approved | STUART CHAPMAN |
| Final | 2/2/2022 | Permit Finaled | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 2/2/2022 | Approved | STUART CHAPMAN |