3475 S STEWART AVE 90066
Certificate Information: 3475 S STEWART AVE 90066
- Application / Permit
- 21016-30000-13056
- Plan Check / Job No.
- B21WL02207
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) Detached garage to an ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/3/2022
- Issuing Office
- Current Status
- CofO Issued on 5/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | ALFREDO JARA |
| Corrections Issued | 6/1/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 10/13/2021 | JASON JANGADA |
| Applicant returned to address corrections | 2/25/2022 | JASON JANGADA |
| Applicant returned to address corrections | 5/5/2022 | JASON JANGADA |
| Plan Check Approved | 5/20/2022 | JASON JANGADA |
| Building Plans Picked Up | 5/24/2022 | APPLICANT |
| Issued | 6/3/2022 | APPLICANT |
| CofO in Progress | 5/4/2023 | RICHARD STEINBACH |
| Permit Finaled | 5/5/2023 | DANIEL ORRANTE |
| CofO Issued | 5/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/7/2021 | WALTER RAMIREZ |
| Grading Pre-Inspection | Cleared | 6/15/2021 | BRIAN MILLER |
| Address approval | Cleared | 6/18/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 6/18/2021 | DINAH GARIN |
| Sewer availability | Cleared | 6/18/2021 | DINAH GARIN |
| Specific Plan | Cleared | 7/22/2021 | PEDRO AYALA |
| Hydrant and Access approval | Cleared | 9/3/2021 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/30/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/1/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 9/14/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/20/2022 | Partial Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 9/20/2022 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/4/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 11/4/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 11/4/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 11/22/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 11/22/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 11/22/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 11/22/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/22/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 12/2/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 12/2/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 12/2/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 12/2/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Drywall Nailing | 12/9/2022 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 12/9/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| Drywall Nailing | 12/14/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 12/14/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 12/14/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 4/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 4/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 5/2/2023 | Approved | JESUS RODRIGUEZ |
| Final | 5/2/2023 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Final | 5/2/2023 | Approved | JESUS RODRIGUEZ |