14315 W HATTERAS ST 91401

Certificate Information: 14315 W HATTERAS ST 91401

Application / Permit
21016-30000-12800
Plan Check / Job No.
B21WL02177
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing 20'x20' detached garage to ADU per CA Govt. Code 65852.2(e)(1)(A). Construction per WFPP, Equipped throughout with NFPA 13D Fire Sprinklers.
Permit Issued
Issued on 9/8/2021
Issuing Office
Current Status
CofO Issued on 11/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2021 APPLICANT
Assigned to Plan Check Engineer 5/21/2021 KAVIAN REFAHI
Corrections Issued 5/21/2021 KAVIAN REFAHI
Plan Check Approved 9/8/2021 VLADIMIR ARUTYUNYAN
Issued 9/8/2021 APPLICANT
CofO in Progress 9/21/2023 RYAN SALAZAR
CofO Issued 11/14/2023 RUBEN SALAS
Permit Finaled 11/14/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/2/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/2/2021 CARLOS AGUILERA
Sewer availability Cleared 6/2/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 6/29/2021 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/25/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 5/9/2022 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 5/9/2022 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 6/2/2022 No Access for Inspection RICHARD DOCKUS
Green Building Rough 6/2/2022 No Access for Inspection RICHARD DOCKUS
HVAC-Rough 6/2/2022 No Access for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 6/3/2022 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 6/13/2022 No Access for Inspection DAVID MATSON
Green Building Rough 6/13/2022 No Access for Inspection DAVID MATSON
Insulation 6/27/2022 Approved MICHAEL SMITH
Drywall Nailing 7/7/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 1/10/2023 Corrections Issued JOHN COLEMAN
HVAC-Final 1/10/2023 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Final 1/10/2023 Corrections Issued JOHN COLEMAN
BUILDING-Rough-Frame 6/28/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 6/28/2023 Approved RYAN SALAZAR
Final 6/28/2023 Partial Approval RYAN SALAZAR
Green Building Final 6/28/2023 Approved RYAN SALAZAR
Green Building Rough 6/28/2023 Approved RYAN SALAZAR
HVAC-Final 6/28/2023 Approved RYAN SALAZAR
PLUMBING-Final 6/28/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 6/28/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 6/28/2023 Approved RYAN SALAZAR
Final 9/20/2023 OK to Issue CofO RYAN SALAZAR