778 E SUNSET AVE 90291
Certificate Information: 778 E SUNSET AVE 90291
- Application / Permit
- 21016-30000-12755
- Plan Check / Job No.
- B21WL02162
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached storage to ADU per CA G.C.S. 65852.2(e)(1)(A) at rear of the lot.
- Permit Issued
- Issued on 6/16/2022
- Issuing Office
- Current Status
- CofO Issued on 1/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 5/22/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 8/3/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 8/18/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 8/24/2021 | ALFREDO JARA |
| Plan Check Approved | 6/4/2022 | DAVID CASTILLO |
| Issued | 6/16/2022 | APPLICANT |
| Building Plans Picked Up | 6/22/2022 | APPLICANT |
| CofO in Progress | 1/21/2023 | RICHARD STEINBACH |
| Permit Finaled | 1/26/2023 | DANIEL ORRANTE |
| CofO Issued | 1/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2021 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 9/29/2021 | JOHN CONNEALLY |
| Coastal Zone | Cleared | 5/24/2022 | DANIEL CORONADO |
| Specific Plan | Cleared | 5/24/2022 | DANIEL CORONADO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/29/2022 | Partial Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 7/7/2022 | Partial Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 7/11/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 7/11/2022 | Partial Approval | DAVID FEILER |
| Deputy Drilled-In Anchors | 7/21/2022 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 7/27/2022 | Partial Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 8/10/2022 | Not Ready for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 8/16/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 8/19/2022 | Partial Approval | DAVID FEILER |
| Deputy Drilled-In Anchors | 9/2/2022 | No Access for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 9/6/2022 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 9/9/2022 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 9/13/2022 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 10/7/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 10/7/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Rough | 10/11/2022 | No Access for Inspection | DAVID FEILER |
| PLUMBING-Rough | 10/11/2022 | No Access for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 10/18/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 10/18/2022 | Approved | DAVID FEILER |
| PLUMBING-Rough | 10/18/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 10/20/2022 | No Access for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 10/20/2022 | No Access for Inspection | DAVID FEILER |
| Green Building Rough | 10/20/2022 | No Access for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 10/21/2022 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2022 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 10/28/2022 | Approved | DAVID FEILER |
| Green Building Rough | 10/28/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 10/28/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 11/2/2022 | Approved | DAVID FEILER |
| Deputy Wood Construction | 11/2/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 11/2/2022 | Approved | DAVID FEILER |
| Insulation | 11/2/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 11/7/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 11/7/2022 | Partial Approval | DAVID FEILER |
| Shower Pan | 11/7/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 11/9/2022 | Not Ready for Inspection | DAVID FEILER |
| Special/Order Compliance | 11/9/2022 | Partial Inspection | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 11/10/2022 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 11/15/2022 | Approved | DAVID FEILER |
| Pre-Inspection | 1/13/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 1/20/2023 | Approved | EVAN COOPER |
| Final | 1/20/2023 | OK to Issue CofO | EVAN COOPER |
| Green Building Final | 1/20/2023 | Approved | EVAN COOPER |
| HVAC-Final | 1/20/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 1/20/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/20/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 1/20/2023 | Approved | EVAN COOPER |