2550 N LA CONDESA DR 90049

Certificate Information: 2550 N LA CONDESA DR 90049

Application / Permit
21016-30000-12675
Plan Check / Job No.
B21WL02148
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel (E) 2-story SFD Per engineering design. No square footage added.
Permit Issued
Issued on 9/2/2021
Issuing Office
Current Status
Permit Finaled on 12/29/2022

Permit Application Status History

Submitted 5/14/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 ALFREDO JARA
Corrections Issued 5/26/2021 ALFREDO JARA
Applicant returned to address corrections 7/1/2021 JASON JANGADA
Plan Check Approved 7/20/2021 ALFREDO JARA
Issued 9/2/2021 APPLICANT
Permit Finaled 12/29/2022 JUAN VALENZUELA

Permit Application Clearance Information

ZA Case Cleared 6/17/2021 RICHARD REASER
Grading Pre-Inspection Cleared 6/21/2021 BRIAN MILLER

Contact Information

Contractor M B S General Construction; Lic. No.: 1049701-B 3102 W CUBBON ST      SANTA ANA, CA 92704
Engineer Song,, Zhenyu Michael; Lic. No.: S5266 12631 IMPERIAL HWY F-230      SANTA FE SPRINGS, CA 90670

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/15/2021 Approved JUAN VALENZUELA
PLUMBING-Rough 10/27/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Shower Pan 10/27/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Shower Pan 10/29/2021 Approved DANIEL ORRANTE
Interior/Exterior Lathing 11/8/2021 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 12/2/2021 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Rough 12/2/2021 Corrections Issued JUAN VALENZUELA
HVAC-Rough 12/2/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 12/2/2021 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 12/6/2021 Approved JUAN VALENZUELA
ELECTRICAL-Rough 12/6/2021 Approved JUAN VALENZUELA
HVAC-Rough 12/6/2021 Approved JUAN VALENZUELA
PLUMBING-Rough 12/6/2021 Approved JUAN VALENZUELA
Insulation 12/8/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 12/8/2021 Approved JUAN VALENZUELA
Drywall Nailing 12/13/2021 Approved KRISTEN CAUSEY
ELECTRICAL-Final 12/6/2022 Not Ready for Inspection DAVID FEILER
Final 12/6/2022 Corrections Issued DAVID FEILER
PLUMBING-Final 12/6/2022 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Not Ready DAVID FEILER
Smoke Detectors 12/6/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 12/13/2022 Approved KENNETH NAGLE
Final 12/13/2022 Corrections Issued KENNETH NAGLE
PLUMBING-Final 12/13/2022 Approved KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Approved KENNETH NAGLE
Smoke Detectors 12/13/2022 Approved KENNETH NAGLE
Special/Order Compliance 12/13/2022 Corrections Issued KENNETH NAGLE
Final 12/29/2022 Permit Finaled JUAN VALENZUELA