7851 S BLERIOT AVE 90045
Certificate Information: 7851 S BLERIOT AVE 90045
- Application / Permit
- 21016-30000-12604
- Plan Check / Job No.
- B21WL02109
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (n) ADU conversion from Detached garage and Workshop with vaulted ceiling Per State Law: CA Govt.Code 65852.2 (e) (1) (A)
- Permit Issued
- Issued on 12/14/2021
- Issuing Office
- Current Status
- CofO Issued on 8/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | KHUONG TRUONG |
| Corrections Issued | 5/22/2021 | KHUONG TRUONG |
| Applicant returned to address corrections | 10/6/2021 | KHUONG TRUONG |
| Applicant returned to address corrections | 10/19/2021 | KHUONG TRUONG |
| Plan Check Approved | 12/14/2021 | KAVIAN REFAHI |
| Issued | 12/14/2021 | APPLICANT |
| Building Plans Picked Up | 3/23/2022 | APPLICANT |
| CofO in Progress | 8/1/2023 | BOBBY KEY |
| Permit Finaled | 8/15/2023 | DANIEL ORRANTE |
| CofO Issued | 8/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2021 | DINAH GARIN |
| Sewer availability | Cleared | 6/14/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 7/30/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 8/3/2021 | RIDWAN HARDY |
| Specific Plan | Cleared | 8/27/2021 | PETE EYRE |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 11/5/2021 | KHUONG TRUONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/2/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 7/6/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 7/6/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 7/6/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 7/8/2022 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 7/8/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 7/20/2022 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 7/20/2022 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 7/25/2022 | Conditional Approval | ANDREW NAVE |
| Green Building Rough | 7/25/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 7/25/2022 | Partial Inspection | ANDREW NAVE |
| Shower Pan | 7/25/2022 | Approved | ANDREW NAVE |
| Deputy Wood Construction | 7/26/2022 | Conditional Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 7/28/2022 | Approved | BOBBY KEY |
| Insulation | 7/28/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 8/24/2022 | Partial Inspection | HERBERT GIRON |
| Final | 8/24/2022 | Corrections Issued | HERBERT GIRON |
| Sewer | 10/4/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 3/21/2023 | Approved | BOBBY KEY |
| Final | 3/21/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 3/21/2023 | Approved | BOBBY KEY |
| HVAC-Final | 3/21/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/21/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 3/21/2023 | Not Ready for Inspection | BOBBY KEY |
| Final | 4/6/2023 | Not Ready for Inspection | RICHARD STEINBACH |
| PLUMBING-Final | 4/6/2023 | Not Ready for Inspection | RICHARD STEINBACH |
| Smoke Detectors | 4/6/2023 | Corrections Issued | RICHARD STEINBACH |
| Final | 4/10/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 4/10/2023 | Not Ready for Inspection | BOBBY KEY |
| Smoke Detectors | 4/10/2023 | Approved | BOBBY KEY |
| Final | 8/1/2023 | OK to Issue CofO | BOBBY KEY |
| PLUMBING-Final | 8/1/2023 | Approved | BOBBY KEY |