7851 S BLERIOT AVE 90045

Certificate Information: 7851 S BLERIOT AVE 90045

Application / Permit
21016-30000-12604
Plan Check / Job No.
B21WL02109
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(n) ADU conversion from Detached garage and Workshop with vaulted ceiling Per State Law: CA Govt.Code 65852.2 (e) (1) (A)
Permit Issued
Issued on 12/14/2021
Issuing Office
Current Status
CofO Issued on 8/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 KHUONG TRUONG
Corrections Issued 5/22/2021 KHUONG TRUONG
Applicant returned to address corrections 10/6/2021 KHUONG TRUONG
Applicant returned to address corrections 10/19/2021 KHUONG TRUONG
Plan Check Approved 12/14/2021 KAVIAN REFAHI
Issued 12/14/2021 APPLICANT
Building Plans Picked Up 3/23/2022 APPLICANT
CofO in Progress 8/1/2023 BOBBY KEY
Permit Finaled 8/15/2023 DANIEL ORRANTE
CofO Issued 8/15/2023 DANIEL ORRANTE
Permit Finaled 8/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/14/2021 DINAH GARIN
Sewer availability Cleared 6/14/2021 DINAH GARIN
Hydrant and Access approval Cleared 7/30/2021 MATTHEW CRAIG
Construction near power lines Cleared 8/3/2021 RIDWAN HARDY
Specific Plan Cleared 8/27/2021 PETE EYRE
Eng Process Fee Ord 176,300 Cleared 10/19/2021 DINAH GARIN
Grading Pre-Inspection Cleared 11/5/2021 KHUONG TRUONG

Contact Information

Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/2/2022 Approved BOBBY KEY
ELECTRICAL-Rough 7/6/2022 Corrections Issued HERBERT GIRON
HVAC-Rough 7/6/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 7/6/2022 Approved HERBERT GIRON
ELECTRICAL-Rough 7/8/2022 Partial Approval BOBBY KEY
HVAC-Rough 7/8/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 7/20/2022 Corrections Issued STEPHANIE SWANSON
Shower Pan 7/20/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 7/25/2022 Conditional Approval ANDREW NAVE
Green Building Rough 7/25/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 7/25/2022 Partial Inspection ANDREW NAVE
Shower Pan 7/25/2022 Approved ANDREW NAVE
Deputy Wood Construction 7/26/2022 Conditional Approval RICHARD STEINBACH
BUILDING-Rough-Frame 7/28/2022 Approved BOBBY KEY
Insulation 7/28/2022 Approved BOBBY KEY
Drywall Nailing 8/24/2022 Partial Inspection HERBERT GIRON
Final 8/24/2022 Corrections Issued HERBERT GIRON
Sewer 10/4/2022 Approved BOBBY KEY
ELECTRICAL-Final 3/21/2023 Approved BOBBY KEY
Final 3/21/2023 Corrections Issued BOBBY KEY
Green Building Final 3/21/2023 Approved BOBBY KEY
HVAC-Final 3/21/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 3/21/2023 Not Ready for Inspection BOBBY KEY
Final 4/6/2023 Not Ready for Inspection RICHARD STEINBACH
PLUMBING-Final 4/6/2023 Not Ready for Inspection RICHARD STEINBACH
Smoke Detectors 4/6/2023 Corrections Issued RICHARD STEINBACH
Final 4/10/2023 Not Ready for Inspection BOBBY KEY
PLUMBING-Final 4/10/2023 Not Ready for Inspection BOBBY KEY
Smoke Detectors 4/10/2023 Approved BOBBY KEY
Final 8/1/2023 OK to Issue CofO BOBBY KEY
PLUMBING-Final 8/1/2023 Approved BOBBY KEY