4713 W BEVERLY BLVD 90004
Certificate Information: 4713 W BEVERLY BLVD 90004
- Application / Permit
- 21016-30000-12368
- Plan Check / Job No.
- B21WL02040
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing storage room inside an apartment building to accessory dwelling unit per GCS 65852.2(e)(1)(C), replace existing slab and lower the floor to increase the ceiling height to 7'-8"
- Permit Issued
- Issued on 6/2/2022
- Issuing Office
- Current Status
- CofO Issued on 1/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | RICHARD GARCIA |
| Corrections Issued | 5/16/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 7/13/2021 | KHUONG TRUONG |
| Applicant returned to address corrections | 7/29/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 9/26/2021 | RICHARD GARCIA |
| Plan Check Approved | 10/19/2021 | RICHARD GARCIA |
| Plan Check Approved | 10/19/2021 | EDWIN ESPIN |
| Issued | 6/2/2022 | APPLICANT |
| Building Plans Picked Up | 6/7/2022 | APPLICANT |
| CofO in Progress | 1/18/2023 | JONATHAN QUACH |
| CofO Issued | 1/18/2023 | TED RIES |
| Permit Finaled | 1/18/2023 | TED RIES |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2021 | WALLIE JONG |
| Sewer availability | Cleared | 6/8/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2021 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 7/2/2021 | RICHARD BRINSON |
| Hydrant and Access approval | Cleared | 7/26/2021 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 7/28/2021 | KHUONG TRUONG |
Contact Information
| Architect | Bowen,, James William; Lic. No.: C20199 | 6204 VISTA DEL MAR APT #275 PLAYA DEL REY, CA 90293 |
| Contractor | Ludwig S C Construction Llc; Lic. No.: 991853-B | 3969 ALLA RD LOS ANGELES, CA 90066 |
| Engineer | Galbreath,, Sean; Lic. No.: S5653 | 600 SOUTH LAKE AVE STE 308 PASADENA, CA 91106 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/9/2022 | Approved | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 6/17/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Other (see comments) | 6/17/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Reinf. Concrete | 6/17/2022 | Conditional Approval | WINSTON DUNNING |
| Footing/Foundation/Slab | 6/17/2022 | Partial Approval | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 6/21/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Other (see comments) | 6/21/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 6/21/2022 | Conditional Approval | ERNESTO CORRAL |
| Footing/Foundation/Slab | 6/28/2022 | Approved | TIMOTHY BUXTON |
| Green Building Rough | 8/8/2022 | Approved | GREGORY POMISH |
| Wood Frame | 8/8/2022 | Approved | GREGORY POMISH |
| Insulation | 8/12/2022 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 8/23/2022 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Not Ready | JONATHAN QUACH |
| Final | 10/28/2022 | Conditional Approval | JONATHAN QUACH |
| Green Building Final | 10/28/2022 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 10/28/2022 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 10/28/2022 | Approved | JONATHAN QUACH |
| Final | 12/1/2022 | Conditional Approval | JONATHAN QUACH |
| Final | 12/13/2022 | Conditional Approval | JONATHAN QUACH |
| Special/Order Compliance | 12/13/2022 | Approved | JONATHAN QUACH |