10791 W LINDBROOK DR 90024

Certificate Information: 10791 W LINDBROOK DR 90024

Application / Permit
21016-30000-11832
Plan Check / Job No.
B21WL01975
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (e) detached garage to accessory dwelling unit per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 8/18/2021
Issuing Office
Current Status
CofO Issued on 4/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 MARJAN SHENASI
Corrections Issued 5/15/2021 MARJAN SHENASI
Applicant returned to address corrections 6/13/2021 RICHARD GARCIA
Plan Check Approved 8/11/2021 JASON JANGADA
Issued 8/18/2021 APPLICANT
CofO in Progress 1/24/2022 BRENDAN LOONEY
Permit Finaled 4/26/2022 DANIEL ORRANTE
CofO Issued 4/26/2022 DANIEL ORRANTE
Permit Finaled 4/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/21/2021 DINAH GARIN
Sewer availability Cleared 5/21/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/25/2021 DINAH GARIN
Grading Pre-Inspection Cleared 6/1/2021 PATRICK MISCHLICH
Specific Plan Cleared 7/1/2021 PETE EYRE
Hydrant and Access approval Cleared 8/3/2021 MATTHEW CRAIG

Contact Information

Architect Lindfors,, Douglas A; Lic. No.: C27129 991 RICHARDSON AVENUE      SIMI VALLEY, CA 93065
Contractor Reyes Edy; Lic. No.: 990315-B 4333 MULTNOMAH STREET      LOS ANGELES, CA 90032

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 8/30/2021 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 11/8/2021 Approved GERMAN RODRIGUEZ MENDOZA
Gas Test 11/8/2021 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 11/8/2021 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 11/8/2021 Approved GERMAN RODRIGUEZ MENDOZA
Shower Pan 11/8/2021 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 12/28/2021 Approved GERMAN RODRIGUEZ MENDOZA
Final 12/28/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
METHANE-Final 12/28/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 12/28/2021 Approved GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 12/28/2021 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 12/28/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Grounding or Bonding 12/30/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Final 1/3/2022 Not Ready for Inspection BRENDAN LOONEY
Smoke Detectors 1/3/2022 Corrections Issued BRENDAN LOONEY
Final 1/21/2022 OK to Issue CofO BRENDAN LOONEY
Smoke Detectors 1/21/2022 Approved BRENDAN LOONEY