10791 W LINDBROOK DR 90024
Certificate Information: 10791 W LINDBROOK DR 90024
- Application / Permit
- 21016-30000-11832
- Plan Check / Job No.
- B21WL01975
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (e) detached garage to accessory dwelling unit per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/18/2021
- Issuing Office
- Current Status
- CofO Issued on 4/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | MARJAN SHENASI |
| Corrections Issued | 5/15/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 6/13/2021 | RICHARD GARCIA |
| Plan Check Approved | 8/11/2021 | JASON JANGADA |
| Issued | 8/18/2021 | APPLICANT |
| CofO in Progress | 1/24/2022 | BRENDAN LOONEY |
| Permit Finaled | 4/26/2022 | DANIEL ORRANTE |
| CofO Issued | 4/26/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/26/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2021 | DINAH GARIN |
| Sewer availability | Cleared | 5/21/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 6/1/2021 | PATRICK MISCHLICH |
| Specific Plan | Cleared | 7/1/2021 | PETE EYRE |
| Hydrant and Access approval | Cleared | 8/3/2021 | MATTHEW CRAIG |
Contact Information
| Architect | Lindfors,, Douglas A; Lic. No.: C27129 | 991 RICHARDSON AVENUE SIMI VALLEY, CA 93065 |
| Contractor | Reyes Edy; Lic. No.: 990315-B | 4333 MULTNOMAH STREET LOS ANGELES, CA 90032 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/26/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 8/30/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 11/8/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 11/8/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 11/8/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 11/8/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 11/8/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 12/28/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 12/28/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Final | 12/28/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Rough | 12/28/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 12/28/2021 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 12/28/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Grounding or Bonding | 12/30/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 1/3/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Smoke Detectors | 1/3/2022 | Corrections Issued | BRENDAN LOONEY |
| Final | 1/21/2022 | OK to Issue CofO | BRENDAN LOONEY |
| Smoke Detectors | 1/21/2022 | Approved | BRENDAN LOONEY |