4146 S 4TH AVE 90008
Certificate Information: 4146 S 4TH AVE 90008
- Application / Permit
- 21016-30000-11485
- Plan Check / Job No.
- B21WL01915
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- bathroom remodel and relocation of washer/dryer. install EV charging station
- Permit Issued
- Issued on 5/18/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/24/2021
Permit Application Status History
| Submitted | 5/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2021 | ALFREDO JARA |
| Corrections Issued | 5/6/2021 | ALFREDO JARA |
| Plan Check Approved | 5/13/2021 | KHUONG TRUONG |
| Issued | 5/18/2021 | APPLICANT |
| Permit Finaled | 8/24/2021 | DAVID FEILER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Heaven At Hand Construction Llc; Lic. No.: 651033-B | 5296 SANCHEZ DR LOS ANGELES, CA 90008 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 6/18/2021 | Partial Approval | DAVID FEILER |
| Service/Power Release | 6/18/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 6/28/2021 | Approved | DAVID FEILER |
| PLUMBING-Rough | 6/28/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 7/6/2021 | Partial Approval | DAVID FEILER |
| Wood Frame | 7/6/2021 | Approved | DAVID FEILER |
| Insulation | 7/8/2021 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 7/8/2021 | Approved | CALEB MEISTER |
| Drywall Nailing | 7/16/2021 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 7/16/2021 | Approved | HORACE FULTZ |
| Shower Pan | 7/16/2021 | Approved | HORACE FULTZ |
| Final | 8/24/2021 | Permit Finaled | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 8/24/2021 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 8/24/2021 | Approved | DAVID FEILER |