5079 1/4 W PICKFORD ST 90019

Certificate Information: 5079 1/4 W PICKFORD ST 90019

Application / Permit
21016-30000-11470
Plan Check / Job No.
B21WL01909
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (E) attached garage into an ADU.PER GCS 65852.2(e)(1)(C)
Permit Issued
Issued on 9/1/2022
Issuing Office
Current Status
CofO Issued on 2/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 RICHARD GARCIA
Corrections Issued 5/16/2021 RICHARD GARCIA
Applicant returned to address corrections 3/10/2022 RICHARD GARCIA
Applicant returned to address corrections 4/28/2022 JASON JANGADA
Applicant returned to address corrections 5/5/2022 JASON JANGADA
Applicant returned to address corrections 5/7/2022 RICHARD GARCIA
Applicant returned to address corrections 6/28/2022 RICHARD GARCIA
Applicant returned to address corrections 7/14/2022 JASON JANGADA
Building Plans Picked Up 7/20/2022 APPLICANT
Applicant returned to address corrections 7/29/2022 DAVID CASTILLO
Applicant returned to address corrections 8/15/2022 ALFREDO JARA
Plan Check Approved 8/24/2022 ALFREDO JARA
Issued 9/1/2022 APPLICANT
CofO in Progress 1/17/2024 JOSE AVILA
CofO in Progress 1/18/2024 SCOTT FINNILA
No Progress 1/22/2024 SCOTT FINNILA
CofO in Progress 2/6/2024 SCOTT FINNILA
Permit Finaled 2/7/2024 DEROLD HAUFF
CofO Issued 2/7/2024 DEROLD HAUFF
Permit Finaled 2/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/26/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/30/2021 CELINA MORENO
Sewer availability Cleared 12/6/2021 WALLIE JONG
Hydrant and Access approval Cleared 2/23/2022 JOHN CONNEALLY
Construction near power lines Cleared 3/22/2022 RIDWAN HARDY
Construction within easement Cleared 3/22/2022 RIDWAN HARDY
Tenant Habitability Plan Cleared 5/24/2022 ISMAEL HERNANDEZ
Flood clearance Cleared 6/17/2022 BRYAN GATHUKA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/9/2022 Approved JOSE AVILA
ELECTRICAL-Rough 11/15/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 11/15/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 11/16/2022 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 11/16/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 11/22/2022 No Access for Inspection MICHAEL LEWIS
PLUMBING-Rough 11/22/2022 No Access for Inspection MICHAEL LEWIS
PLUMBING-Rough 2/24/2023 Partial Approval JOSE AVILA
Footing/Foundation/Slab 4/26/2023 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/2/2023 Approved JOSE AVILA
HVAC-Rough 5/30/2023 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 6/13/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 6/13/2023 Approved JOSE AVILA
HVAC-Rough 6/13/2023 Approved JOSE AVILA
Rough-Elec/Plmb/HVAC 6/13/2023 Approved JOSE AVILA
ELECTRICAL-Rough 7/7/2023 Conditional Approval JOSE AVILA
Special/Order Compliance 7/7/2023 Conditional Approval RONNIE MINDANAO
Interior/Exterior Lathing 7/20/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 9/20/2023 Approved JOSE AVILA
FLOOD-Elevation Certificate 9/20/2023 Approved JOSE AVILA
FLOOD-Proofing Certificate 9/20/2023 Approved JOSE AVILA
Insulation 10/10/2023 Approved JOSE AVILA
Interior/Exterior Lathing 10/10/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 10/10/2023 SGSOV Approved JOSE AVILA
ELECTRICAL-Final 1/16/2024 Approved JOSE AVILA
Final 1/16/2024 OK to Issue CofO JOSE AVILA
HVAC-Final 1/16/2024 Approved JOSE AVILA
PLUMBING-Final 1/16/2024 Approved JOSE AVILA
Smoke Detectors 1/16/2024 Approved JOSE AVILA
Final 1/17/2024 OK to Issue CofO SCOTT FINNILA
Smoke Detectors 1/17/2024 Approved SCOTT FINNILA