626 1/2 N SILVER LAKE BLVD 90026

Certificate Information: 626 1/2 N SILVER LAKE BLVD 90026

Application / Permit
21016-30000-10746
Plan Check / Job No.
B21WL01804
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU 400SQFT. PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 7/27/2021
Issuing Office
Current Status
CofO Issued on 1/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 KAVIAN REFAHI
Corrections Issued 5/1/2021 KAVIAN REFAHI
Plan Check Approved 7/20/2021 MARJAN SHENASI
Issued 7/27/2021 APPLICANT
CofO in Progress 1/20/2022 ALIZAH MAYAGOITIA
Permit Finaled 1/31/2022 DEROLD HAUFF
CofO Issued 1/31/2022 DEROLD HAUFF
Permit Finaled 1/31/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/11/2021 RENZ SORIANO
Sewer availability Cleared 5/11/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 5/12/2021 RENZ SORIANO
Hydrant and Access approval Cleared 6/29/2021 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 8/20/2021 Not Ready for Inspection ROBERT VORHIS
METHANE-Rough 9/9/2021 No Access for Inspection ROBERT VORHIS
PLUMBING-Rough 9/9/2021 Not Ready for Inspection ROBERT VORHIS
METHANE-Rough 9/17/2021 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 9/17/2021 Partial Approval KATHRYN BUTTERWORTH
Sewer 9/17/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 9/22/2021 Approved ROBERT VORHIS
ELECTRICAL-Rough 10/18/2021 Not Ready for Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Partial Approval ROBERT VORHIS
HVAC-Rough 10/18/2021 Approved ROBERT VORHIS
MERV13>=Rough 10/18/2021 Approved ROBERT VORHIS
METHANE-Rough 10/18/2021 Approved ROBERT VORHIS
PLUMBING-Rough 10/18/2021 Approved ROBERT VORHIS
Wood Frame 10/18/2021 Not Ready for Inspection ROBERT VORHIS
ELECTRICAL-Rough 11/3/2021 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 11/3/2021 Partial Approval ROBERT VORHIS
Interior/Exterior Lathing 11/8/2021 Partial Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 11/16/2021 Approved ADAM ESCOTO
Insulation 11/16/2021 Conditional Approval ADAM ESCOTO
Drywall Nailing 11/22/2021 Approved ROBERT VORHIS
Interior/Exterior Lathing 11/22/2021 Partial Inspection ROBERT VORHIS
Reinforced Masonry Frame 11/22/2021 Not Ready for Inspection ROBERT VORHIS
Final 12/29/2021 Not Ready for Inspection RUBEN SALAS
MERV13>=Final 12/29/2021 Not Ready for Inspection RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 12/29/2021 SGSOV Not Ready RUBEN SALAS
Smoke Detectors 12/29/2021 Not Ready for Inspection RUBEN SALAS
Final 1/6/2022 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Final 1/6/2022 Approved ALIZAH MAYAGOITIA
Insulation 1/6/2022 Approved ALIZAH MAYAGOITIA
MERV13>=Final 1/6/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/6/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 1/6/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 1/13/2022 Corrections Issued ALIZAH MAYAGOITIA
Final 1/13/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Gas Test 1/13/2022 Approved ALIZAH MAYAGOITIA
MERV13>=Final 1/13/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 1/13/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/13/2022 SGSOV Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 1/19/2022 Approved ALIZAH MAYAGOITIA
Final 1/19/2022 OK to Issue CofO ALIZAH MAYAGOITIA