515 N HOMEWOOD ROAD 90049

Certificate Information: 515 N HOMEWOOD ROAD 90049

Application / Permit
21016-30000-10390
Plan Check / Job No.
B21WL01758
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior / exterior alteration to (e) 1-story SFD with att. garage to remodel laundry room, guest room, guest bathroom, and storage areas and partial replacement of the roof
Permit Issued
Issued on 10/15/2021
Issuing Office
Current Status
Permit Finaled on 8/8/2023

Permit Application Status History

Submitted 4/22/2021 APPLICANT
Assigned to Plan Check Engineer 4/23/2021 RICHARD GARCIA
Corrections Issued 4/24/2021 RICHARD GARCIA
Plan Check Approved 6/25/2021 REZA HAGHIGHAT
Issued 10/15/2021 APPLICANT
Building Plans Picked Up 10/19/2021 APPLICANT
Permit Finaled 8/8/2023 KEVIN SARGSYAN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/10/2021 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 5/26/2021 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 5/26/2021 DENNIS BRAGIN
Green Code Cleared 6/25/2021 RICHARD GARCIA

Contact Information

Contractor Bonomo Development; Lic. No.: 669677-B 1523 LINDA COURT      SIMI VALLEY, CA 93065
Engineer Onishi,, Robert K; Lic. No.: S3705 4438 LINDBLADE DRIVE      LOS ANGELES, CA 90066

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/9/2021 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 11/9/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 1/3/2022 Partial Inspection JUAN VALENZUELA
HVAC-Rough 2/11/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 2/11/2022 Approved JUAN VALENZUELA
HVAC-Rough 3/16/2022 Approved JUAN VALENZUELA
PLUMBING-Rough 3/16/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 3/29/2022 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 3/29/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 5/11/2022 Approved STEPHANIE SWANSON
Drywall Nailing 5/11/2022 Approved STEPHANIE SWANSON
Insulation 5/11/2022 Approved STEPHANIE SWANSON
Shower Pan 5/20/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 5/27/2022 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 6/3/2022 Approved JUAN VALENZUELA
ELECTRICAL-Final 7/5/2023 Corrections Issued BRENDAN LOONEY
Green Building Final 7/5/2023 Approved BRENDAN LOONEY
HVAC-Final 7/5/2023 Corrections Issued BRENDAN LOONEY
PLUMBING-Final 7/5/2023 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 8/3/2023 Corrections Issued HERBERT GIRON
HVAC-Final 8/3/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 8/3/2023 Approved HERBERT GIRON
Final 8/8/2023 Permit Finaled KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 8/8/2023 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 8/8/2023 Approved KEVIN SARGSYAN