6922 W 85TH PL 90045

Certificate Information: 6922 W 85TH PL 90045

Application / Permit
21016-30000-10346
Plan Check / Job No.
B21WL01746
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
convert covered area under the second floor to habitable space on the first floor on an existing 2-story SFD
Permit Issued
Issued on 9/20/2021
Issuing Office
Current Status
CofO Issued on 11/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 TARIK SAOUD
Corrections Issued 5/9/2021 TARIK SAOUD
Quality Review Completed 5/12/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 9/14/2021 TARIK SAOUD
Issued 9/20/2021 APPLICANT
CofO in Progress 11/9/2023 BOBBY KEY
Permit Finaled 11/14/2023 DANIEL ORRANTE
CofO Issued 11/14/2023 DANIEL ORRANTE
Permit Finaled 11/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/13/2021 DINAH GARIN
Sewer availability Cleared 5/13/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/14/2021 DINAH GARIN

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: C35389 1810 14TH STREET SUITE 204      SANTA MONICA, CA 90404
Contractor Owner-Builder       ,
Engineer Lotfi,, Fariborz Frank; Lic. No.: C49359 1328 DUENDE LANE      PACIFIC PALISADES, CA 90272

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/16/2021 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 12/28/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 1/24/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Partial Approval BOBBY KEY
Green Building Rough 2/16/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 4/25/2022 Corrections Issued BOBBY KEY
PLUMBING-Rough 4/25/2022 Partial Approval BOBBY KEY
Deputy Wood Construction 4/27/2022 Conditional Approval RYAN SALAZAR
ELECTRICAL-Rough 5/13/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Approved BOBBY KEY
Green Building Rough 5/13/2022 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 5/13/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 6/9/2022 Corrections Issued BOBBY KEY
Green Building Rough 6/9/2022 Corrections Issued BOBBY KEY
Insulation 6/9/2022 Not Ready for Inspection BOBBY KEY
Shower Pan 6/9/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 7/5/2022 Corrections Issued STEPHANIE SWANSON
Green Building Rough 7/5/2022 Approved STEPHANIE SWANSON
Insulation 7/5/2022 Conditional Approval STEPHANIE SWANSON
Interior/Exterior Lathing 7/5/2022 Approved STEPHANIE SWANSON
PLUMBING-Rough 7/5/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 7/7/2022 Approved STEPHANIE SWANSON
Drywall Nailing 7/25/2022 Approved ANDREW NAVE
Green Building Final 10/28/2022 Not Ready for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/28/2022 SGSOV Approved BOBBY KEY
Service/Power Release 10/28/2022 Approved BOBBY KEY
Smoke Detectors 10/28/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 11/10/2022 Conditional Approval BOBBY KEY
Special/Order Compliance 11/29/2022 Partial Inspection BOBBY KEY
ELECTRICAL-Final 6/9/2023 Approved BOBBY KEY
Final 6/9/2023 Corrections Issued BOBBY KEY
Green Building Final 6/9/2023 Approved BOBBY KEY
HVAC-Final 6/9/2023 Corrections Issued BOBBY KEY
PLUMBING-Final 6/9/2023 Corrections Issued BOBBY KEY
Smoke Detectors 6/9/2023 Corrections Issued BOBBY KEY
Underground Mechanical 6/9/2023 Approved BOBBY KEY
Final 10/5/2023 Corrections Issued HERBERT GIRON
Smoke Detectors 10/5/2023 Not Ready for Inspection HERBERT GIRON
Final 11/9/2023 OK to Issue CofO BOBBY KEY
HVAC-Final 11/9/2023 Approved BOBBY KEY
PLUMBING-Final 11/9/2023 Approved BOBBY KEY
Smoke Detectors 11/9/2023 Approved BOBBY KEY