1650 S VICTORIA AVE 90019
Certificate Information: 1650 S VICTORIA AVE 90019
- Application / Permit
- 21016-30000-10240
- Plan Check / Job No.
- B21WL01729
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Structural remodel of an (e) 2-story s.f.d. *** 1 of 3 ***
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/23/2024
Permit Application Status History
| Submitted | 4/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | RICHARD GARCIA |
| Corrections Issued | 5/2/2021 | RICHARD GARCIA |
| Quality Review Completed | 5/12/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 3/7/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 3/31/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 4/12/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 6/24/2022 | RICHARD GARCIA |
| Plan Check Approved | 6/27/2022 | RICHARD GARCIA |
| No Progress | 6/27/2022 | RICHARD GARCIA |
| Plan Check Approved | 8/4/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 10/11/2022 | APPLICANT |
| Issued | 10/27/2022 | APPLICANT |
| Permit Finaled | 4/23/2024 | JUSTIN HAWLEY |
Permit Application Clearance Information
| HPOZ | Cleared | 7/13/2021 | AMANDA KAINER |
| ZI | Cleared | 7/13/2021 | AMANDA KAINER |
Contact Information
| Contractor | Level Frame Construction Inc; Lic. No.: 1078493-B | 1834 W 84TH PL LOS ANGELES, CA 90047 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/7/2022 | Partial Approval | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 1/23/2023 | Conditional Approval | CALEB MEISTER |
| Wood Frame | 2/7/2023 | Not Ready for Inspection | CALEB MEISTER |
| Underground Mechanical | 3/6/2023 | Partial Approval | CALEB MEISTER |
| Deputy Wood Construction | 3/14/2023 | Conditional Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 3/22/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 3/22/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 3/22/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 8/30/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 8/30/2023 | Approved | CALEB MEISTER |
| HVAC-Rough | 8/30/2023 | Approved | CALEB MEISTER |
| Insulation | 8/30/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 8/30/2023 | Partial Approval | CALEB MEISTER |
| PLUMBING-Rough | 8/30/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 9/14/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 11/28/2023 | Approved | BRENDAN MORELLI |
| Shower Pan | 11/28/2023 | Approved | BRENDAN MORELLI |
| Gas Test | 2/26/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Service/Power Release | 2/26/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Gas Test | 2/27/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Service/Power Release | 2/27/2024 | Corrections Issued | JUSTIN HAWLEY |
| Gas Test | 3/1/2024 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 3/1/2024 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 3/1/2024 | Corrections Issued | JUSTIN HAWLEY |
| ELECTRICAL-Final | 3/28/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 3/28/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 3/28/2024 | Approved | JUSTIN HAWLEY |
| Final | 4/4/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 4/4/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Approved | CRAIG DAVIS |
| Smoke Detectors | 4/4/2024 | Approved | CRAIG DAVIS |
| Final | 4/23/2024 | Permit Finaled | JUSTIN HAWLEY |
| Green Building Final | 4/23/2024 | Approved | JUSTIN HAWLEY |