1650 S VICTORIA AVE 90019

Certificate Information: 1650 S VICTORIA AVE 90019

Application / Permit
21016-30000-10240
Plan Check / Job No.
B21WL01729
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Structural remodel of an (e) 2-story s.f.d. *** 1 of 3 ***
Permit Issued
Issued on 10/27/2022
Issuing Office
Metro
Current Status
Permit Finaled on 4/23/2024

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 RICHARD GARCIA
Corrections Issued 5/2/2021 RICHARD GARCIA
Quality Review Completed 5/12/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/7/2022 RICHARD GARCIA
Applicant returned to address corrections 3/31/2022 RICHARD GARCIA
Applicant returned to address corrections 4/12/2022 RICHARD GARCIA
Applicant returned to address corrections 6/24/2022 RICHARD GARCIA
Plan Check Approved 6/27/2022 RICHARD GARCIA
No Progress 6/27/2022 RICHARD GARCIA
Plan Check Approved 8/4/2022 RICHARD GARCIA
Building Plans Picked Up 10/11/2022 APPLICANT
Issued 10/27/2022 APPLICANT
Permit Finaled 4/23/2024 JUSTIN HAWLEY

Permit Application Clearance Information

HPOZ Cleared 7/13/2021 AMANDA KAINER
ZI Cleared 7/13/2021 AMANDA KAINER

Contact Information

Contractor Level Frame Construction Inc; Lic. No.: 1078493-B 1834 W 84TH PL      LOS ANGELES, CA 90047
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/7/2022 Partial Approval STUART CHAPMAN
Deputy Drilled-In Anchors 1/23/2023 Conditional Approval CALEB MEISTER
Wood Frame 2/7/2023 Not Ready for Inspection CALEB MEISTER
Underground Mechanical 3/6/2023 Partial Approval CALEB MEISTER
Deputy Wood Construction 3/14/2023 Conditional Approval CALEB MEISTER
ELECTRICAL-Rough 3/22/2023 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 3/22/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 3/22/2023 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 8/30/2023 Approved CALEB MEISTER
ELECTRICAL-Rough 8/30/2023 Approved CALEB MEISTER
HVAC-Rough 8/30/2023 Approved CALEB MEISTER
Insulation 8/30/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 8/30/2023 Partial Approval CALEB MEISTER
PLUMBING-Rough 8/30/2023 Approved CALEB MEISTER
Drywall Nailing 9/14/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 11/28/2023 Approved BRENDAN MORELLI
Shower Pan 11/28/2023 Approved BRENDAN MORELLI
Gas Test 2/26/2024 Not Ready for Inspection JUSTIN HAWLEY
Service/Power Release 2/26/2024 Not Ready for Inspection JUSTIN HAWLEY
Gas Test 2/27/2024 Not Ready for Inspection JUSTIN HAWLEY
Service/Power Release 2/27/2024 Corrections Issued JUSTIN HAWLEY
Gas Test 3/1/2024 Approved JUSTIN HAWLEY
Service/Power Release 3/1/2024 Approved JUSTIN HAWLEY
Special/Order Compliance 3/1/2024 Corrections Issued JUSTIN HAWLEY
ELECTRICAL-Final 3/28/2024 Approved JUSTIN HAWLEY
HVAC-Final 3/28/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 3/28/2024 Approved JUSTIN HAWLEY
Final 4/4/2024 Corrections Issued CRAIG DAVIS
Green Building Final 4/4/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Approved CRAIG DAVIS
Smoke Detectors 4/4/2024 Approved CRAIG DAVIS
Final 4/23/2024 Permit Finaled JUSTIN HAWLEY
Green Building Final 4/23/2024 Approved JUSTIN HAWLEY