1731 S GARTH AVE 90035

Certificate Information: 1731 S GARTH AVE 90035

Application / Permit
21016-30000-10212
Plan Check / Job No.
B21WL01724
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of an existing detached 2-car garage into an ADU
Permit Issued
Issued on 9/13/2021
Issuing Office
Current Status
Issued on 9/13/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/22/2021 APPLICANT
Assigned to Plan Check Engineer 4/23/2021 RICHARD GARCIA
Corrections Issued 4/24/2021 RICHARD GARCIA
Plan Check Approved 8/19/2021 KHUONG TRUONG
Building Plans Picked Up 8/24/2021 APPLICANT
Issued 9/13/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/6/2021 WALLIE JONG
Sewer availability Cleared 5/6/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 5/7/2021 WALLIE JONG
Hydrant and Access approval Cleared 6/29/2021 KURT CORRAL
Construction near power lines Cleared 8/4/2021 RIDWAN HARDY
Construction within easement Cleared 8/4/2021 RIDWAN HARDY

Contact Information

Architect Scrafano,, Elissa F; Lic. No.: C26071 163 N SYCAMORE      LOS ANGELES, CA 90036
Contractor Manasse Inc; Lic. No.: 607634-B 29059 RAINTREE LN      SAUGUS, CA 91390
Engineer Manalo,, Philip Casis; Lic. No.: S3823 9547 WYSTONE AVE      NORTHRIDGE, CA 91324

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/2/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 11/17/2021 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 11/22/2021 Approved EVAN COOPER
Footing/Foundation/Slab 11/22/2021 Approved EVAN COOPER
ELECTRICAL-Rough 12/13/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 12/13/2021 Partial Approval EVAN COOPER
Sewer 12/13/2021 Partial Approval EVAN COOPER
Underground Mechanical 12/13/2021 Approved EVAN COOPER
Sewer 1/11/2022 Approved EVAN COOPER
Underground Mechanical 1/11/2022 Approved EVAN COOPER
ELECTRICAL-Rough 1/24/2022 Approved EVAN COOPER
HVAC-Rough 1/24/2022 Approved EVAN COOPER
PLUMBING-Rough 1/24/2022 Approved EVAN COOPER
Wood Frame 1/24/2022 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 3/9/2022 Approved EVAN COOPER
ELECTRICAL-Rough 3/9/2022 Approved EVAN COOPER
Green Building Rough 3/9/2022 Approved EVAN COOPER
METHANE-Rough 3/9/2022 Approved EVAN COOPER
PLUMBING-Rough 3/9/2022 Approved EVAN COOPER
Drywall Nailing 3/15/2022 Approved EVAN COOPER
Shower Pan 3/29/2022 Approved EVAN COOPER
Interior/Exterior Lathing 3/31/2022 Approved EVAN COOPER
Final 7/11/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 7/11/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 7/11/2023 SGSOV Not Required ARAM AVEDISIAN
Smoke Detectors 7/11/2023 Approved ARAM AVEDISIAN
Final 7/18/2023 Corrections Issued ARAM AVEDISIAN