414 S LORING AVE 90024

Certificate Information: 414 S LORING AVE 90024

Application / Permit
21016-30000-10202
Plan Check / Job No.
B21WL01713
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
interior and exterior renovation of existing 2-story SFD. existing bay window and patio to be removed.
Permit Issued
Issued on 7/19/2022
Issuing Office
Current Status
CofO Issued on 12/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 4/23/2021 KAVIAN REFAHI
Corrections Issued 4/24/2021 KAVIAN REFAHI
Plan Check Approved 10/4/2021 KHUONG TRUONG
Plan Check Approved 6/22/2022 EDWIN ESPIN
Issued 7/19/2022 APPLICANT
Building Plans Picked Up 8/2/2022 APPLICANT
CofO in Progress 12/8/2023 STEPHANIE SWANSON
Permit Finaled 12/19/2023 DANIEL ORRANTE
CofO Issued 12/19/2023 DANIEL ORRANTE
Permit Finaled 12/19/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/7/2021 DINAH GARIN
Sewer availability Cleared 5/7/2021 DINAH GARIN
CPC Cleared 7/8/2021 MAXFIELD VERMY
Grading Pre-Inspection Cleared 7/20/2021 KAVIAN REFAHI

Contact Information

Contractor Mike Nicholls Construction; Lic. No.: 815861-B 3835 EAST THOUSAND OAKS BLVD   #309    WESTLAKE VILLAGE, CA 91362
Engineer Manalo,, Philip Casis; Lic. No.: S3823 9547 WYSTONE AVE      NORTHRIDGE, CA 91324

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/16/2022 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 11/17/2022 Partial Approval STEPHANIE SWANSON
Wood Frame 12/1/2022 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 12/8/2022 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 2/3/2023 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 3/14/2023 Partial Approval STEPHANIE SWANSON
Wood Frame 3/14/2023 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 6/15/2023 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 6/15/2023 Approved STEPHANIE SWANSON
PLUMBING-Rough 6/15/2023 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 6/26/2023 Partial Approval STEPHANIE SWANSON
Drywall Nailing 6/26/2023 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/26/2023 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 11/27/2023 Approved STEPHANIE SWANSON
Final 11/27/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 11/27/2023 Approved STEPHANIE SWANSON
Green Building Final 11/27/2023 Approved STEPHANIE SWANSON
Green Building Rough 11/27/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 11/27/2023 Corrections Issued STEPHANIE SWANSON
Final 12/8/2023 OK to Issue CofO STEPHANIE SWANSON
Smoke Detectors 12/8/2023 Approved STEPHANIE SWANSON