759 N WILDOMAR ST 90272
Certificate Information: 759 N WILDOMAR ST 90272
- Application / Permit
- 21016-30000-09754
- Plan Check / Job No.
- B21WL01668
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU PER CA GCS 65852.2(e)(1)(A) AT REAR OF THE LOT.
- Permit Issued
- Issued on 12/13/2021
- Issuing Office
- Current Status
- CofO Issued on 5/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2021 | KAVIAN REFAHI |
| Corrections Issued | 4/24/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 9/28/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 12/3/2021 | MARJAN SHENASI |
| Issued | 12/13/2021 | APPLICANT |
| Building Plans Picked Up | 12/20/2021 | APPLICANT |
| CofO in Progress | 5/12/2023 | GERMAN RODRIGUEZ MENDOZA |
| Permit Finaled | 5/15/2023 | DANIEL ORRANTE |
| CofO Issued | 5/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/7/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 6/7/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2021 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 6/21/2021 | KIRK LINKLATER |
| Construction near power lines | Cleared | 8/4/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 9/13/2021 | GILBERT URREA |
Contact Information
| Architect | Mackler,, Deborah Ellen; Lic. No.: C35957 | 334 SYCAMORE ROAD SANTA MONICA, CA 90402 |
| Contractor | Espana Building And Remodeling Inc; Lic. No.: 607889-B | 23027 W ERWIN STREET WOODLAND HILLS, CA 91367 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/21/2021 | Approved | ANDREW NAVE |
| Deputy Drilled-In Anchors | 1/14/2022 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Partial Approval | ANDREW NAVE |
| Underground Mechanical | 1/21/2022 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 1/24/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/24/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 2/8/2022 | Partial Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 2/23/2022 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 2/23/2022 | Corrections Issued | ANDREW NAVE |
| BUILDING-Rough-Frame | 3/7/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 3/7/2022 | Approved | ANDREW NAVE |
| HVAC-Rough | 3/7/2022 | Conditional Approval | ANDREW NAVE |
| Insulation | 3/7/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 3/7/2022 | Approved | ANDREW NAVE |
| Drywall Nailing | 5/3/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/3/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/4/2022 | Approved | ANDREW NAVE |
| HVAC-Rough | 5/4/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 5/4/2022 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 7/6/2022 | Corrections Issued | JOHN KIDWELL |
| Interior/Exterior Lathing | 7/8/2022 | Approved | HERBERT GIRON |
| Final | 4/21/2023 | Corrections Issued | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 4/21/2023 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 4/21/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 5/3/2023 | Corrections Issued | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 5/3/2023 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 5/3/2023 | Approved | BRENDAN LOONEY |
| Final | 5/8/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |