8418 1/2 S GLIDER AVE 90045

Certificate Information: 8418 1/2 S GLIDER AVE 90045

Application / Permit
21016-30000-09697
Plan Check / Job No.
B21WL01658
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached rec. room and garage into an ADU with attached storage and garage. PER GCS 65852.2(e)(1)(D)
Permit Issued
Issued on 10/13/2021
Issuing Office
Current Status
CofO Issued on 5/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/21/2021 ALFREDO JARA
Corrections Issued 4/23/2021 ALFREDO JARA
Applicant returned to address corrections 7/20/2021 ALFREDO JARA
Plan Check Approved 9/29/2021 ALFREDO JARA
Issued 10/13/2021 APPLICANT
CofO in Progress 4/12/2022 BOBBY KEY
No Progress 4/15/2022 RICHARD STEINBACH
CofO in Progress 4/27/2022 RICHARD STEINBACH
Permit Finaled 5/5/2022 DANIEL ORRANTE
CofO Issued 5/5/2022 DANIEL ORRANTE
Permit Finaled 5/5/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 6/22/2021 PEDRO AYALA
Tenant Habitability Plan Cleared 6/29/2021 ISMAEL HERNANDEZ
Address approval Cleared 7/8/2021 SAUL GARCIA
Sewer availability Cleared 7/8/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 7/13/2021 SAUL GARCIA
Construction near power lines Cleared 8/24/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 9/12/2021 ROBERT DUFF

Contact Information

Contractor Stonecastle Construction & Development Corp; Lic. No.: 601665-B 8330 LILIENTHAL AVE   UNIT B    LOS ANGELES, CA 90045

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/20/2021 Approved ENRIQUE MIRELES
HVAC-Rough 10/20/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 10/20/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 10/20/2021 Approved ENRIQUE MIRELES
Wood Frame 10/20/2021 Approved ENRIQUE MIRELES
Drywall Nailing 10/27/2021 Approved BOBBY KEY
Insulation 10/27/2021 Approved BOBBY KEY
Interior/Exterior Lathing 10/27/2021 Partial Approval BOBBY KEY
Gas Test 10/28/2021 Approved BOBBY KEY
Pre-Inspection 10/28/2021 Partial Inspection DAVID FEILER
Service/Power Release 10/28/2021 Partial Inspection BOBBY KEY
Shower Pan 10/28/2021 Not Ready for Inspection BOBBY KEY
Shower Pan 11/2/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 3/22/2022 Approved BOBBY KEY
ELECTRICAL-Final 3/22/2022 Corrections Issued BOBBY KEY
Final 3/22/2022 Corrections Issued BOBBY KEY
HVAC-Final 3/22/2022 Approved BOBBY KEY
Interior/Exterior Lathing 3/22/2022 Approved BOBBY KEY
PLUMBING-Final 3/22/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV Approved BOBBY KEY
Service/Power Release 3/22/2022 Not Ready for Inspection BOBBY KEY
Smoke Detectors 3/22/2022 Approved BOBBY KEY
ELECTRICAL-Final 4/8/2022 Approved BOBBY KEY
Final 4/8/2022 Not Ready for Inspection BOBBY KEY
Final 4/12/2022 OK to Issue CofO BOBBY KEY
Service/Power Release 4/12/2022 Approved BOBBY KEY
Special/Order Compliance 4/18/2022 Corrections Issued BOBBY KEY