8418 1/2 S GLIDER AVE 90045
Certificate Information: 8418 1/2 S GLIDER AVE 90045
- Application / Permit
- 21016-30000-09697
- Plan Check / Job No.
- B21WL01658
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached rec. room and garage into an ADU with attached storage and garage. PER GCS 65852.2(e)(1)(D)
- Permit Issued
- Issued on 10/13/2021
- Issuing Office
- Current Status
- CofO Issued on 5/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2021 | ALFREDO JARA |
| Corrections Issued | 4/23/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 7/20/2021 | ALFREDO JARA |
| Plan Check Approved | 9/29/2021 | ALFREDO JARA |
| Issued | 10/13/2021 | APPLICANT |
| CofO in Progress | 4/12/2022 | BOBBY KEY |
| No Progress | 4/15/2022 | RICHARD STEINBACH |
| CofO in Progress | 4/27/2022 | RICHARD STEINBACH |
| Permit Finaled | 5/5/2022 | DANIEL ORRANTE |
| CofO Issued | 5/5/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/5/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/22/2021 | PEDRO AYALA |
| Tenant Habitability Plan | Cleared | 6/29/2021 | ISMAEL HERNANDEZ |
| Address approval | Cleared | 7/8/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 7/8/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | SAUL GARCIA |
| Construction near power lines | Cleared | 8/24/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 9/12/2021 | ROBERT DUFF |
Contact Information
| Contractor | Stonecastle Construction & Development Corp; Lic. No.: 601665-B | 8330 LILIENTHAL AVE UNIT B LOS ANGELES, CA 90045 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/20/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/20/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/20/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/20/2021 | Approved | ENRIQUE MIRELES |
| Wood Frame | 10/20/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/27/2021 | Approved | BOBBY KEY |
| Insulation | 10/27/2021 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/27/2021 | Partial Approval | BOBBY KEY |
| Gas Test | 10/28/2021 | Approved | BOBBY KEY |
| Pre-Inspection | 10/28/2021 | Partial Inspection | DAVID FEILER |
| Service/Power Release | 10/28/2021 | Partial Inspection | BOBBY KEY |
| Shower Pan | 10/28/2021 | Not Ready for Inspection | BOBBY KEY |
| Shower Pan | 11/2/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 3/22/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 3/22/2022 | Corrections Issued | BOBBY KEY |
| Final | 3/22/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 3/22/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 3/22/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 3/22/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 3/22/2022 | Not Ready for Inspection | BOBBY KEY |
| Smoke Detectors | 3/22/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 4/8/2022 | Approved | BOBBY KEY |
| Final | 4/8/2022 | Not Ready for Inspection | BOBBY KEY |
| Final | 4/12/2022 | OK to Issue CofO | BOBBY KEY |
| Service/Power Release | 4/12/2022 | Approved | BOBBY KEY |
| Special/Order Compliance | 4/18/2022 | Corrections Issued | BOBBY KEY |